VERVE

by KOLTE-PATIL DEVELOPERS LIMITED Company
Certificate Signed P51800028783
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51800028783
Registration No.
REA51800086106
Registration Date
2021-09-08
Developer
KOLTE-PATIL DEVELOPERS LIMITED Company
Architect
Reza Kabul
Project Bank
AXIS BANK
Proposed Possession
2025-07-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
8
Project Area
9420.53 sq.m
Total FSI
29416.04
Approved FSI
29416.04
MahaRERA QR
VERVE
MahaRERA — P51800028783
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors25
Sanctioned25
🅿️Closed Parking86
📅Completion2024-07-31
📅Completion2024-07-31
🏗️Proposed Floors2
Sanctioned2
🚗Open Parking2
🅿️Closed Parking10
📅Completion2024-07-31
🏗️Proposed Floors24
Sanctioned24
🅿️Closed Parking96
📅Completion2024-07-31
🏗️Proposed Floors4
Sanctioned4
🚗Open Parking8
🅿️Closed Parking32
📅Completion2025-01-31
🏗️Proposed Floors33
Sanctioned33
🅿️Closed Parking135
📅Completion2025-01-31
🏗️Proposed Floors5
Sanctioned5
🚗Open Parking9
🅿️Closed Parking36
📅Completion2025-01-31
🏗️Proposed Floors32
Sanctioned32
🅿️Closed Parking129
📅Completion2025-01-31

Apartment Configurations

Wing A - Ground To 15Th Floor

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 66.16 14 14 0
100%
2 BHK 66.63 14 14 0
100%
2 BHK 70.52 15 15 0
100%
3 BHK 95.12 15 15 0
100%
Ground Floor Shop 1 111.74 1 1 0
100%
Ground Floor Shop 2 68.62 1 1 0
100%
Ground Floor Shop 3 66.58 1 1 0
100%

Wing A -16Th Floor

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 66.16 1 1 0
100%
2 BHK 66.63 1 1 0
100%
2 BHK 70.52 1 1 0
100%
3 BHK 95.12 1 1 0
100%

Wing B - 15Th And 16Th Floor

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 70.47 2 2 0
100%
2 BHK 70.55 2 2 0
100%
3 BHK 95.05 2 2 0
100%
3 BHK 95.08 2 2 0
100%

Wing B - Ground To 14Th Floor

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 70.47 14 14 0
100%
2 BHK 70.55 13 13 0
100%
3 BHK 95.05 14 14 0
100%
3 BHK 95.08 14 14 0
100%
Ground Floor Shop 4 78.65 1 1 0
100%
Ground Floor Shop 5 66.64 1 1 0
100%
Ground Floor Shop 6 68.47 1 1 0
100%
Ground Floor Shop 7 111.74 1 1 0
100%

Wing C - 24 To 27 Floor

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 70.52 3 1 2
33%
2 BHK 70.54 4 3 1
75%
3 BHK 95.93 3 3 0
100%
3 BHK 95.97 4 3 1
75%
3 BHK 111.06 1 1 0
100%

Wing C - Ground To 23Rd Floor

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 70.52 23 19 4
83%
2 BHK 70.54 22 22 0
100%
3 BHK 95.93 20 19 1
95%
3 BHK 95.97 22 22 0
100%

Wing D - 23Rd To 27Th Floor

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 70.47 4 4 0
100%
2 BHK 70.54 5 2 3
40%
3 BHK 95.96 5 5 0
100%
3 BHK 95.97 4 4 0
100%
3 BHK 111.06 1 1 0
100%

Wing D - Ground To 22Nd Floor

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 66.2 18 18 0
100%
2 BHK 70.47 22 22 0
100%
2 BHK 70.54 3 3 0
100%
3 BHK 95.96 21 21 0
100%
3 BHK 95.97 19 18 1
95%

Construction Progress

Wing A - Ground to 15th Floor

Basement (if any)0%

Wing A - Ground To 15Th Floor

Excavation100%

Wing A - Ground to 15th Floor

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing A - Ground To 15Th Floor

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

Wing A - Ground to 15th Floor

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing A - Ground To 15Th Floor

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

Wing A - Ground to 15th Floor

Plinth0%
Podiums (if any) 100%

Wing A - Ground To 15Th Floor

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

Wing A - Ground to 15th Floor

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing A - Ground To 15Th Floor

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

Wing A - Ground to 15th Floor

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing A - Ground To 15Th Floor

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth0%
X number of Podiums100%
X number of Slabs of Super Structure100%

Wing A -16th Floor

Basement (if any)0%

Wing A -16Th Floor

Excavation0%

Wing A -16th Floor

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing A -16Th Floor

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

Wing A -16th Floor

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing A -16Th Floor

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing60%

Wing A -16th Floor

Plinth0%
Podiums (if any) 0%

Wing A -16Th Floor

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

Wing A -16th Floor

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing A -16Th Floor

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

Wing A -16th Floor

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing A -16Th Floor

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure100%

Wing B - 15th and 16th Floor

Basement (if any)0%

Wing B - 15Th And 16Th Floor

Excavation0%

Wing B - 15th and 16th Floor

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing B - 15Th And 16Th Floor

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

Wing B - 15th and 16th Floor

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing B - 15Th And 16Th Floor

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing60%

Wing B - 15th and 16th Floor

Plinth0%
Podiums (if any) 0%

Wing B - 15Th And 16Th Floor

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

Wing B - 15th and 16th Floor

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing B - 15Th And 16Th Floor

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

Wing B - 15th and 16th Floor

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing B - 15Th And 16Th Floor

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure100%

Wing B - Ground to 14th floor

Basement (if any)0%

Wing B - Ground To 14Th Floor

Excavation100%

Wing B - Ground to 14th floor

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing B - Ground To 14Th Floor

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%

Wing B - Ground to 14th floor

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing B - Ground To 14Th Floor

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%

Wing B - Ground to 14th floor

Plinth0%
Podiums (if any) 100%

Wing B - Ground To 14Th Floor

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%

Wing B - Ground to 14th floor

Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%

Wing B - Ground To 14Th Floor

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

Wing B - Ground to 14th floor

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing B - Ground To 14Th Floor

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth0%
X number of Podiums100%
X number of Slabs of Super Structure100%

Wing C - 24 to 27 Floor

Basement (if any)0%

Wing C - 24 To 27 Floor

Excavation0%

Wing C - 24 to 27 Floor

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing C - 24 To 27 Floor

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate90%

Wing C - 24 to 27 Floor

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing C - 24 To 27 Floor

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing49%

Wing C - 24 to 27 Floor

Plinth0%
Podiums (if any) 0%

Wing C - 24 To 27 Floor

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

Wing C - 24 to 27 Floor

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Wing C - 24 To 27 Floor

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

Wing C - 24 to 27 Floor

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing C - 24 To 27 Floor

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure100%

Wing C - Ground to 23rd Floor

Basement (if any)0%

Wing C - Ground To 23Rd Floor

Excavation100%

Wing C - Ground to 23rd Floor

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing C - Ground To 23Rd Floor

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate90%

Wing C - Ground to 23rd Floor

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing C - Ground To 23Rd Floor

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing79%

Wing C - Ground to 23rd Floor

Plinth0%
Podiums (if any) 100%

Wing C - Ground To 23Rd Floor

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

Wing C - Ground to 23rd Floor

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Wing C - Ground To 23Rd Floor

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

Wing C - Ground to 23rd Floor

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing C - Ground To 23Rd Floor

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth0%
X number of Podiums100%
X number of Slabs of Super Structure100%

Wing D - 23rd to 27th Floor

Basement (if any)0%

Wing D - 23Rd To 27Th Floor

Excavation0%

Wing D - 23rd to 27th Floor

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing D - 23Rd To 27Th Floor

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate95%

Wing D - 23rd to 27th Floor

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%

Wing D - 23Rd To 27Th Floor

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises95%
Overall Percentage of Completion of the work done For the entire Building /Wing49%

Wing D - 23rd to 27th Floor

Plinth0%
Podiums (if any) 0%

Wing D - 23Rd To 27Th Floor

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

Wing D - 23rd to 27th Floor

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Wing D - 23Rd To 27Th Floor

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

Wing D - 23rd to 27th Floor

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing D - 23Rd To 27Th Floor

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure100%

Wing D - Ground to 22nd Floor

Basement (if any)0%

Wing D - Ground To 22Nd Floor

Excavation100%

Wing D - Ground to 22nd Floor

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%

Wing D - Ground To 22Nd Floor

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate95%

Wing D - Ground to 22nd Floor

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Wing D - Ground To 22Nd Floor

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises95%
Overall Percentage of Completion of the work done For the entire Building /Wing79%

Wing D - Ground to 22nd Floor

Plinth0%
Podiums (if any) 100%

Wing D - Ground To 22Nd Floor

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

Wing D - Ground to 22nd Floor

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Wing D - Ground To 22Nd Floor

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

Wing D - Ground to 22nd Floor

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Wing D - Ground To 22Nd Floor

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth0%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 100%
Energy management 80%
Fire Protection And Fire Safety Requirements 100%
Fitness Centre 90%
Landscaping & Tree Planting 100%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 100%
Solid Waste Management And Disposal 90%
Storm Water Drains 100%
Street Lighting 85%
Treatment And Disposal Of Sewage And Sullage Water 100%
Water Conservation, Rain water Harvesting 100%
Water Supply 100%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.