📞 +91 98200 30685 ✉️
RERA: A51800043517

Vista

by ELITE HOUSING LLP Partnership
Certificate Signed P51800046797
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P51800046797
Registration No.
REA51800115843
Registration Date
2022-09-10
Developer
ELITE HOUSING LLP Partnership
Architect
Pushkar Consultants
Project Bank
HDFC BANK
Proposed Possession
2025-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
677.05 sq.m
Total FSI
2444.72
Approved FSI
2444.72
MahaRERA QR
Vista
MahaRERA — P51800046797
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors15
Sanctioned15
⬇️Basements1
🅿️Closed Parking21
📅Completion2025-12-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 46.970001220703125 0 0 0
0%
2Bhk 71.0999984741211 0 0 0
0%
3Bhk 103.05000305175781 0 0 0
0%

Vista

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 46.97 1 1 0
100%
2 BHK 71.1 7 4 3
57%
3 BHK 103.05 5 1 4
20%

Construction Progress

Vista

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing79%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises50%
Sanitary Fittings within the flats / premises50%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
Stilt Floor85%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing90%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 50%
Energy management
Fire Protection And Fire Safety Requirements 90%
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP) 90%
Solid Waste Management And Disposal 90%
Storm Water Drains 90%
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water 90%
Water Conservation, Rain water Harvesting 100%
Water Supply 50%
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.