Project Information

RERA Certificate No.
P51700022773
Registration No.
REA51700062996
Registration Date
2024-04-24
Developer
PEER REALTY PRIVATE LIMITED Company
Project Bank
HDFC BANK
Proposed Possession
2025-10-30
Revised Possession
1900-01-01
Extended Possession
2028-09-30
Units Sold
0
Buildings
5
Project Area
19599.00 sq.m
Total FSI
94075.20
Approved FSI
86799.98
MahaRERA QR
OPULUS S1 S2 R1 R2 and R3
MahaRERA — P51700022773
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors31
Sanctioned31
🅿️Closed Parking133
📅Completion2025-10-30
🏗️Proposed Floors31
Sanctioned31
🅿️Closed Parking172
📅Completion2025-10-30
🏗️Proposed Floors34
Sanctioned34
🅿️Closed Parking174
📅Completion2025-10-30
🏗️Proposed Floors40
Sanctioned40
🅿️Closed Parking246
📅Completion2025-10-30
🏗️Proposed Floors39
Sanctioned39
🅿️Closed Parking246
📅Completion2025-10-30

Apartment Configurations

Opulus R1

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 47.47 36 0 36
0%
2 BHK 50.62 47 0 47
0%
4.5 BHK 95.26 33 0 33
0%

Opulus R2

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 50.13 46 0 46
0%
2 BHK 56.88 47 0 47
0%
2 BHK 56.9 20 0 20
0%
2 BHK 60.65 6 0 6
0%
2 BHK 68.47 15 0 15
0%
4.5 BHK 102.38 15 0 15
0%

Opulus R3

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 47.4 56 0 56
0%
2 BHK 47.81 50 0 50
0%
2 BHK 61.38 58 0 58
0%

Opulus S1

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 55.95 68 16 52
24%
2 BHK 55.97 61 21 40
34%
2 BHK 56.36 1 0 1
0%
2 BHK 56.44 2 0 2
0%
2 BHK 63.37 34 13 21
38%
2 BHK 63.45 1 0 1
0%
2 BHK 63.82 34 10 24
29%
2 BHK 63.89 1 0 1
0%
3 BHK 77.95 34 8 26
24%
3 BHK 78.18 1 0 1
0%
3 BHK 78.5 34 13 21
38%
3 BHK 78.74 1 0 1
0%

Opulus S2

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 55.95 68 0 68
0%
2 BHK 55.97 61 0 61
0%
2 BHK 63.37 34 0 34
0%
2 BHK 63.82 34 0 34
0%
3 BHK 77.95 34 0 34
0%
3 BHK 78.5 34 0 34
0%

Construction Progress

OPULUS R1

Basement (if any)0%

Opulus R1

Excavation0%

OPULUS R1

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Opulus R1

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

OPULUS R1

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Opulus R1

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

OPULUS R1

Plinth0%
Podiums (if any) 0%

Opulus R1

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

OPULUS R1

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Opulus R1

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

OPULUS R1

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Opulus R1

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

OPULUS R2

Basement (if any)98%

Opulus R2

Excavation100%

OPULUS R2

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Opulus R2

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

OPULUS R2

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Opulus R2

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%

OPULUS R2

Plinth98%
Podiums (if any) 98%

Opulus R2

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

OPULUS R2

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure8%

Opulus R2

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

OPULUS R2

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Opulus R2

Stilt Floor95%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth95%
X number of Podiums95%
X number of Slabs of Super Structure15%

OPULUS R3

Basement (if any)98%

Opulus R3

Excavation100%

OPULUS R3

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Opulus R3

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

OPULUS R3

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Opulus R3

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%

OPULUS R3

Plinth98%
Podiums (if any) 98%

Opulus R3

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

OPULUS R3

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure3%

Opulus R3

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

OPULUS R3

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Opulus R3

Stilt Floor95%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth95%
X number of Podiums95%
X number of Slabs of Super Structure0%

OPULUS S1

Basement (if any)98%

Opulus S1

Excavation100%

OPULUS S1

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Opulus S1

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

OPULUS S1

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Opulus S1

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%

OPULUS S1

Plinth98%
Podiums (if any) 98%

Opulus S1

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

OPULUS S1

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure5%

Opulus S1

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

OPULUS S1

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Opulus S1

Stilt Floor95%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth95%
X number of Podiums95%
X number of Slabs of Super Structure0%

OPULUS S2

Basement (if any)0%

Opulus S2

Excavation50%

OPULUS S2

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Opulus S2

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

OPULUS S2

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Opulus S2

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

OPULUS S2

Plinth0%
Podiums (if any) 0%

Opulus S2

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

OPULUS S2

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Opulus S2

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

OPULUS S2

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Opulus S2

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.