Project Information

RERA Certificate No.
P51700022773
Registration No.
REA51700062996
Registration Date
2024-04-24
Developer
PEER REALTY PRIVATE LIMITED Company
Project Bank
HDFC BANK
Proposed Possession
2025-10-30
Revised Possession
1900-01-01
Extended Possession
2028-09-30
Units Sold
0
Buildings
5
Project Area
19599.00 sq.m
Total FSI
94075.20
Approved FSI
86799.98
MahaRERA QR
OPULUS S1 S2 R1 R2 and R3
MahaRERA — P51700022773
Scan to verify on MahaRERA portal

Wing-wise Details

šŸ—ļøProposed Floors31
āœ…Sanctioned31
šŸ…æļøClosed Parking133
šŸ“…Completion2025-10-30
šŸ—ļøProposed Floors31
āœ…Sanctioned31
šŸ…æļøClosed Parking172
šŸ“…Completion2025-10-30
šŸ—ļøProposed Floors34
āœ…Sanctioned34
šŸ…æļøClosed Parking174
šŸ“…Completion2025-10-30
šŸ—ļøProposed Floors40
āœ…Sanctioned40
šŸ…æļøClosed Parking246
šŸ“…Completion2025-10-30
šŸ—ļøProposed Floors39
āœ…Sanctioned39
šŸ…æļøClosed Parking246
šŸ“…Completion2025-10-30

Apartment Configurations

Opulus R1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK47.4736036
0%
2 BHK50.6247047
0%
4.5 BHK95.2633033
0%

Opulus R2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK50.1346046
0%
2 BHK56.8847047
0%
2 BHK56.920020
0%
2 BHK60.65606
0%
2 BHK68.4715015
0%
4.5 BHK102.3815015
0%

Opulus R3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK47.456056
0%
2 BHK47.8150050
0%
2 BHK61.3858058
0%

Opulus S1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK55.95681652
24%
2 BHK55.97612140
34%
2 BHK56.36101
0%
2 BHK56.44202
0%
2 BHK63.37341321
38%
2 BHK63.45101
0%
2 BHK63.82341024
29%
2 BHK63.89101
0%
3 BHK77.9534826
24%
3 BHK78.18101
0%
3 BHK78.5341321
38%
3 BHK78.74101
0%

Opulus S2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK55.9568068
0%
2 BHK55.9761061
0%
2 BHK63.3734034
0%
2 BHK63.8234034
0%
3 BHK77.9534034
0%
3 BHK78.534034
0%

Construction Progress

OPULUS R1

Basement (if any)0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

OPULUS R2

Basement (if any)98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth98%
Podiums (if any) 98%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure8%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

OPULUS R3

Basement (if any)98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth98%
Podiums (if any) 98%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure3%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

OPULUS S1

Basement (if any)98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth98%
Podiums (if any) 98%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure5%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

OPULUS S2

Basement (if any)0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Opulus R1

Excavation0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

Opulus R2

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor95%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth95%
X number of Podiums95%
X number of Slabs of Super Structure15%

Opulus R3

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor95%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth95%
X number of Podiums95%
X number of Slabs of Super Structure0%

Opulus S1

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor95%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth95%
X number of Podiums95%
X number of Slabs of Super Structure0%

Opulus S2

Excavation50%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

RERA Registered Amenities

āœ…Aggregate area of recreational Open Space
⬜Community Buildings
āœ…Electrical Meter Room, Sub-Station, Receiving Station
āœ…Energy management
āœ…Fire Protection And Fire Safety Requirements
āœ…Landscaping & Tree Planting
āœ…Open Parking
āœ…Sewerage (Chamber, Lines, Septic Tank , STP)
āœ…Solid Waste Management And Disposal
āœ…Storm Water Drains
āœ…Street Lighting
āœ…Treatment And Disposal Of Sewage And Sullage Water
āœ…Water Conservation, Rain water Harvesting
āœ…Water Supply
CallWhatsApp
āœ‰ļø

Get in Touch

Our team will connect with you shortly

+91
šŸ”’ Your details are secure with us
⚔ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
šŸ‘‹ Looking for the right project? Let me help you find it!
šŸ—ļø
MPE Project Advisor
ā— Online now