Project Information

RERA Certificate No.
P51700000636
Registration No.
REA51700004144
Registration Date
2021-09-09
Developer
Chaurang Associates Others
Architect
Nambarch
Project Bank
STATE BANK OF INDIA
Proposed Possession
2022-03-30
Revised Possession
2022-03-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
3
Project Area
666.20 sq.m
Total FSI
2344.68
Approved FSI
594.68
MahaRERA QR
Swiss Boulevard
MahaRERA — P51700000636
Scan to verify on MahaRERA portal

Wing-wise Details

šŸ—ļøProposed Floors6
āœ…Sanctioned6
šŸ…æļøClosed Parking10
šŸ“…Completion2020-03-31
šŸ—ļøProposed Floors7
āœ…Sanctioned7
šŸ…æļøClosed Parking10
šŸ“…Completion2020-03-31
šŸ—ļøProposed Floors2
āœ…Sanctioned2
šŸ“…Completion1900-01-01

Apartment Configurations

Swiss Boulevard Phase 1-1St To 4Th Floor

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2bhk60.2101
0%
2bhk68.61220
100%

Swiss Boulevard Phase 2 - 5Th-11Th Floor

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2Bhk67.88101
0%
3 BHK80.35404
0%
3 BHK93.38303
0%

Swiss Boulevard Phase 3 - 12Th And 13Th Floor

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3 BHK80.48202
0%
3 BHK94.56202
0%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2Bhk60.20000076293945000
0%
2Bhk67.87999725341797000
0%
2Bhk68.61000061035156000
0%
3Bhk80.3499984741211000
0%
3Bhk80.4800033569336000
0%
3Bhk93.37999725341797000
0%
3Bhk94.55999755859375000
0%

Construction Progress

Swiss Boulevard Phase 1-1St To 4Th Floor

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Swiss Boulevard Phase 1-1st to 4th Floor

Basement (if any)100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Swiss Boulevard Phase 2 - 5Th-11Th Floor

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Swiss Boulevard Phase 2 - 5th-11th floor

Basement (if any)100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Swiss Boulevard Phase 3 - 12Th And 13Th Floor

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

Swiss Boulevard Phase 3 - 12th and 13th floor

Basement (if any)100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
āœ…Electrical Meter Room, Sub-Station, Receiving Station
⬜Energy management
āœ…Fire Protection And Fire Safety Requirements
⬜Landscaping & Tree Planting
⬜Open Parking
āœ…Sewerage (Chamber, Lines, Septic Tank , STP)
⬜Solid Waste Management And Disposal
āœ…Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
⬜Water Conservation, Rain water Harvesting
āœ…Water Supply
CallWhatsApp
āœ‰ļø

Get in Touch

Our team will connect with you shortly

+91
šŸ”’ Your details are secure with us
⚔ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
šŸ‘‹ Looking for the right project? Let me help you find it!
šŸ—ļø
MPE Project Advisor
ā— Online now