List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Aarya Prem Co-Op Hsg Soc

by K S Builders & Developers Partnership
Certificate SignedP51700054798
Aarya Prem Co-Op Hsg SocProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700054798
Registration No.
REA51700150067
Registration Date
2024-02-12
Developer
K S Builders & Developers Partnership
Architect
R M Wakhar
Project Bank
TJSB SAHAKARI BANK LTD
Proposed Possession
2027-02-28
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
48
Units Sold
19 (40%)
Buildings
1
Project Area
837.81 sq.m
Total FSI
2252.97
Approved FSI
2252.97
MahaRERA QR
Aarya Prem Co-Op Hsg Soc
MahaRERA — P51700054798
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors9
✅Sanctioned9
🏠Habitable7
🔢Total Units48
🏡Residential42
🏢Non-Residential6

Apartment Configurations

AARYA PREM CO OP HSG SOC

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK32.9414014
0%
1BHK34.4716
14%
1BHK34.7202
0%
2BHK33.79716
14%
2BHK42.47505
0%
2BHK44.92505
0%
3BHK52.64211
50%
Shop13.56101
0%
Shop13.67101
0%
Shop14.53101
0%
Shop17.33101
0%
Shop17.47202
0%

Construction Progress

AARYA PREM CO OP HSG SOC

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises50%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
✅Fire protection and fire safety requirements
⬜Internal Roads & Footpaths
⬜Landscaping & Tree Planting
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
⬜Solid Waste Management And Disposal
✅Storm Water Drains
✅Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting

Latest Mumbai Property News

View all news →
CallWhatsApp
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor