List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Abhilash Phase Ii

by Sanjona Builders Partnership
Certificate SignedP51800033199
Abhilash Phase IiProject photos will appear here when available.

Project Information

RERA Certificate No.
P51800033199
Registration No.
REA51800101929
Registration Date
2022-02-09
Developer
Sanjona Builders Partnership
Architect
Vishaarad Architects
Project Bank
IDBI BANK
Proposed Possession
2027-03-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
14
Units Sold
6 (43%)
Buildings
1
Project Area
383.66 sq.m
Total FSI
1009.47
Approved FSI
1009.47
MahaRERA QR
Abhilash Phase Ii
MahaRERA — P51800033199
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors5
✅Sanctioned5
🏠Habitable5
🔢Total Units14
🏡Residential14

Apartment Configurations

Abhilash Phase II

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK93.83202
0%
4BHK123.84660
100%

Construction Progress

Abhilash Phase II

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station100%
⬜Energy managemcnt
✅Fire protection and fire safety requirements100%
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting100%
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
✅Solid Waste Management And Disposal100%
✅Storm Water Drains100%
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply100%
⬜Water conservation /Rain water harvesting