Abhilash

by Sanjona Builders
Kept in AbeyanceP51800001840
AbhilashProject photos will appear here when available.

Project Information

RERA Certificate No.
P51800001840
Registration No.
REA51800007829
Developer
Sanjona Builders
Project Bank
HDFC BANK
Proposed Possession
2017-12-30
Revised Possession
2018-12-31
Extended Possession
2022-03-30
Buildings
1
Project Area
1894.67 sq.m
Total FSI
3917.50
Approved FSI
910.94
MahaRERA QR
Abhilash
MahaRERA — P51800001840
Scan to verify on MahaRERA portal

Wing-wise Details

🚗Open Parking7
🅿️Closed Parking57
📅Completion2018-12-31

Apartment Configurations

Abhilash

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3 BHK88.75550
100%
3 BHK88.94110
100%
3 BHK90.61660
100%
3 BHK90.99110
100%
3 BHK98.51110
100%
3 BHK102.7330
100%
4 BHK100.0110
100%
4 BHK116.91110
100%
4 BHK117.1220
100%
4 BHK117.47220
100%
4 BHK117.57110
100%
4 BHK120.82110
100%
4 BHK127.04303
0%
4 BHK136.06303
0%

Construction Progress

Abhilash

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate70%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises77%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises77%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.77%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing77%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure78%

RERA Registered Amenities

✅Aggregate area of recreational Open Space70%
⬜Community Buildings
✅Electrical Meter Room, Sub-Station, Receiving Station75%
⬜Energy management
✅Fire Protection And Fire Safety Requirements75%
✅Landscaping & Tree Planting70%
✅Open Parking80%
✅Sewerage (Chamber, Lines, Septic Tank , STP)90%
⬜Solid Waste Management And Disposal
✅Storm Water Drains90%
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Conservation, Rain water Harvesting70%
✅Water Supply90%