List PropertyWhatsApp
New ProjectsBuy a FlatRent a FlatCommercialBuilders & DevelopersWhy UsRERA SearchLocalitiesTools & CalculatorsNRI HubNews+ List Your PropertyπŸ’¬ WhatsApp Us
🏠 Mumbai property advisory & dataOperating since 1995βœ“ MahaRERA A51800043517βœ“ RERA-verified project data🟒 We reply in minutes on WhatsApp
A
βœ“ MahaRERA P99000006132βœ“ Clear

Acropolis 2 by Bhoomi & Arkade Associates

πŸ“ Virar West, Palghar Β· 401303
526
Units
2022
Possession
6
Buildings
Certificate Signed
Status
01

Possession Timeline

Proposed
Dec 2022
Revised
Dec 2022
Status
Ongoing
02

Unit Configurations (per MahaRERA)

ConfigurationCarpetIndicative Price
1 BHK326–345 ftΒ²On request
1.5 BHK456–460 ftΒ²On request
2 BHK488–529 ftΒ²On request
Shop94–675 ftΒ²On request
Configurations & carpet per MahaRERA filing Β· indicative price = locality rate Γ— carpet (not the developer's quote).
πŸ’¬ Live availability, floor plans & today's price β€” on WhatsApp
03

RERA Trust Record

MahaRERA No.
P99000006132
Registered
2021-09-09
Litigation
None on record
Escrow Bank
KOTAK MAHINDRA BANK LIMITED
Architect
Reza Kabul
Total FSI
19946
04

Buildings Β· 6 Wing(s)

A17 floors Β· β€” units
B17 floors Β· β€” units
C17 floors Β· β€” units
D17 floors Β· β€” units
E17 floors Β· β€” units
F17 floors Β· β€” units
05

Land DNA Β· Genesis

Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06

Location

πŸ“ Virar West
19.469215999999999,72.796919000000003
β–Έ Explore map & Street View β€” for verified buyers
07

Promoter & Professionals

Arkade Developers Private Limited Arkade Developers Private LimitedPartner
Bhoomi Shashwat Estate Private Limited Bhoomi Shashwat Estate Private LimitedPartner
09

Construction Progress

100% avg
Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Plinth100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
10

Amenities

Aggregate area of recreational Open SpaceElectrical Meter Room, Sub-Station, Receiving StationEnergy managementFire Protection And Fire Safety RequirementsLandscaping & Tree PlantingPodium with ClubhouseSewerage (Chamber, Lines, Septic Tank , STP)Solid Waste Management And DisposalStorm Water DrainsStreet LightingTreatment And Disposal Of Sewage And Sullage WaterWater Conservation, Rain water HarvestingWater Supply
12

Floor Plans, E-Brochure & Payment Plans

πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13

EMI Calculator

β€”
14

More by Bhoomi & Arkade Associates

Bhoomi AmoghAndheri West Β· Under ConstructionBhoomi Simana Tower CParel Β· Under ConstructionBhoomi LakescapeThane West Β· Under ConstructionKalash GreensNew Panvel Β· Under ConstructionBhoomi AcresThane West Β· Under ConstructionBhoomi PratishtaBorivali West Β· Under Construction
15

MahaRERA projects nearby in Virar West

MAYFAIR VIRAR GARDENS BUILDING NO 17, 18, 19, 23A, 26, 27901 unitsYASHWANT AVENUE 2209 unitsVIVA CITY - A3140 unitsVIVA CITY - A4138 unitsYASHWANT PRESTIGE112 unitsSHANTI NIWAS108 unitsMAHAVIR ASHISH CO-OPERATIVE HOUSING SOCIETY LTD78 unitsYASHWANT CIRCLE70 unitsAvanti Heights70 unitsSHREE GAYATRI CHSL56 unitsHIRUBAI RESIDENCY39 unitsSHREE SHIVKRUPA CO OPERATIVE HOUSING SOCIETY LIMITED31 units
?

Frequently Asked Questions

When is possession of ACROPOLIS 2?

As per MahaRERA, proposed possession is Dec 2022, revised to Dec 2022.

Is ACROPOLIS 2 RERA-registered?

Yes β€” MahaRERA registration P99000006132, registered 2021-09-09. No litigations on record.

Who is the developer?

Bhoomi & Arkade Associates β€” 55 projects tracked on Mumbai Property Exchange. View their track record β–Έ

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Virar West β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
Our advisor replies on WhatsApp within 2 working hours (9am–8pm IST).
βœ“ MahaRERA P51900079270β˜… Featured
Runwal Enterprises
7 Mahalaxmi, Mahalaxmi
2 BHK, 3 BHK, 4 BHK Β· β‚Ή56,000/sq.ft Β· Possession Dec 2031
Learn more β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’