Advance LegacyProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700021688
Registration No.
REA51700058756
Registration Date
2022-02-16
Developer
Ramesh Dungarshi Shah Individual
Architect
Bhirud & Associates
Project Bank
IDBI BANK
Proposed Possession
2023-12-30
Revised Possession
1900-01-01
Extended Possession
2024-06-30
Units Sold
0
Buildings
2
Project Area
3035.15 sq.m
Total FSI
4950.31
Approved FSI
4950.31
MahaRERA QR
Advance Legacy
MahaRERA — P51700021688
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors8
Sanctioned8
🏗️Proposed Floors8
Sanctioned8

Apartment Configurations

ADVANCE LEGACY - A WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK32.76303
0%
1BHK33.17404
0%
1BHK36.99303
0%
1BHK37.04404
0%
2BHK58.74404
0%
2BHK59.16312
33%

ADVANCE LEGACY B-WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK32.62404
0%
1BHK32.64440
100%
1BHK32.76271215
44%
1BHK32.9404
0%
1BHK33.05312
33%
1BHK33.1722139
59%
1BHK33.49321
67%
1RK23.81550
100%
1RK24.22321
67%

Construction Progress

ADVANCE LEGACY - A WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

ADVANCE LEGACY B-WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)100%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical meter room, sub-station, receiving station
Energy managemcnt
Fire protection and fire safety requirements
Internal Roads & Footpaths
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Supply
Water conservation /Rain water harvesting