List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Advent Palazzo

by Advent Developers Private Limited Company
Certificate SignedP51800002649
Advent PalazzoProject photos will appear here when available.

Project Information

RERA Certificate No.
P51800002649
Registration No.
REA51800008278
Registration Date
2017-08-02
Developer
Advent Developers Private Limited Company
Architect
Mrs Supriya Vaidya Concrete Designs
Project Bank
INDIAN BANK
Proposed Possession
2018-06-30
Revised Possession
2018-06-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
1975.00 sq.m
Total FSI
5059.16
Approved FSI
4895.87
MahaRERA QR
Advent Palazzo
MahaRERA — P51800002649
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors25
✅Sanctioned25

Apartment Configurations

Advent Palazzo

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1RK32.041046
40%
2BHK64.531046
40%
2BHK68.831248
33%
2BHK74.26101
0%
3BHK80.371367
46%
3BHK80.6213310
23%
3BHK103.5202
0%
3BHK109.97101
0%
3BHK121.9202
0%

Construction Progress

Advent Palazzo

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises85%
Plinth100%
Podiums (if any)95%
Sanitary Fittings within the flats / premises50%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor90%

RERA Registered Amenities

✅Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
✅Fire protection and fire safety requirements60%
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting10%
✅Open Parking60%
✅Sewerage (Chamber, Lines, Septic Tank , STP)85%
✅Society Office
✅Solid Waste Management And Disposal
✅Storm Water Drains85%
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply65%
✅Water conservation /Rain water harvesting80%