Amber TaraProject photos will appear here when available.
Project Information
RERA Certificate No.
P51700020065
Registration No.
REA51700054024
Registration Date
2021-09-09
Developer
Ambercorporation Partnership
Architect
Sthapatya Nirmaan
Project Bank
IDBI BANK
Proposed Possession
2025-12-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
828.10 sq.m
Total FSI
999.90
Approved FSI
724.90
Amber Tara
MahaRERA — P51700020065
MahaRERA — P51700020065
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors7
✅Sanctioned7
Apartment Configurations
AMBER TARA
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1BHK | 36.3 | 5 | 4 | 1 | 80% |
| 1BHK | 38.75 | 1 | 1 | 0 | 100% |
| 1BHK | 40.7 | 5 | 2 | 3 | 40% |
| 1BHK | 40.97 | 4 | 3 | 1 | 75% |
| 1RK | 26.01 | 4 | 2 | 2 | 50% |
| 1RK | 27.97 | 1 | 1 | 0 | 100% |
Construction Progress
AMBER TARA
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station100%
⬜Energy managemcnt
✅Fire protection and fire safety requirements100%
⬜Internal Roads & Footpaths
⬜Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
⬜Solid Waste Management And Disposal
⬜Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting100%