42
Units
2024
Possession
1
Buildings
Certificate Signed
Status
01

Possession Timeline

Proposed
Jun 2024
Status
New
02

Unit Configurations (per MahaRERA)

ConfigurationCarpetIndicative Price
1 RK241 ftΒ²On request
2 BHK327–395 ftΒ²On request
1 BHK250–445 ftΒ²On request
Configurations & carpet per MahaRERA filing Β· indicative price = locality rate Γ— carpet (not the developer's quote).
πŸ’¬ Live availability, floor plans & today's price β€” on WhatsApp
03

RERA Trust Record

MahaRERA No.
P51700033708
Registered
2022-03-02
Litigation
None on record
Escrow Bank
IDBI BANK
Architect
Mahesh Jagtap And Associates
Total FSI
2018
04

Buildings Β· 1 Wing(s)

Amreshwar Co-Operative Housing Society Limited9 floors Β· β€” units
05

Land DNA Β· Genesis

Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06

Location

πŸ“ Kansai
β–Έ Explore map & Street View β€” for verified buyers
07

Promoter & Professionals

SPG BUILDERS AND DEVELOPERSNA
09

Construction Progress

64% avg
Basement (if any)100%
Excavation100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor 100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
10

Amenities

Landscaping & Tree PlantingLandscaping & Tree PlantingSewerage (Chamber, Lines, Septic Tank , STP)Water Conservation, Rain water HarvestingWater SupplyWater conservation /Rain water harvesting
12

Floor Plans, E-Brochure & Payment Plans

πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13

EMI Calculator

β€”
15

MahaRERA projects nearby in Kansai

Ragas Times Square74 unitsChaitraban Chs28 unitsIshwar Saraswati Palace26 unitsKanchan Ganga24 unitsIshwar Blossom23 unitsShree Gurukrupa20 unitsShreeyug Residency17 unitsMadhusudan Building13 unitsGulmohar Chs LtdSHREE SAI ARNAVHare Krishna Janvi HeightIndira Sadan Phase I
?

Frequently Asked Questions

When is possession of Amreshwar Co-Operative Housing Society Limited?

As per MahaRERA, proposed possession is Jun 2024.

Is Amreshwar Co-Operative Housing Society Limited RERA-registered?

Yes β€” MahaRERA registration P51700033708, registered 2022-03-02. No litigations on record.

Who is the developer?

Spg Builders And Developers View their track record β–Έ

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Kansai β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
Our advisor replies on WhatsApp within 2 working hours (9am–8pm IST).
βœ“ MahaRERA P51900079270β˜… Featured
Runwal Enterprises
7 Mahalaxmi, Mahalaxmi
2 BHK, 3 BHK, 4 BHK Β· β‚Ή56,000/sq.ft Β· Possession Dec 2031
Learn more β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’