List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Anantya 1A

by Radius &Amp; Deserve Builders Llp
Certificate SignedP51800005533
Anantya 1AProject photos will appear here when available.

Project Information

RERA Certificate No.
P51800005533
Registration No.
REA51800015378
Developer
Radius &Amp; Deserve Builders Llp
Architect
Girish Chaudhari
Project Bank
Yes Bank Ltd
Proposed Possession
2025-12-30
Revised Possession
2025-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
5
Project Area
13577.40 sq.m
Total FSI
74564.47
Approved FSI
21530.00
MahaRERA QR
Anantya 1A
MahaRERA — P51800005533
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors49
✅Sanctioned49
🏗️Proposed Floors37
✅Sanctioned37
🏗️Proposed Floors37
✅Sanctioned37
🏗️Proposed Floors48
✅Sanctioned48
🏗️Proposed Floors48
✅Sanctioned48

Apartment Configurations

TOWER 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK A 145.832320
100%
1 BHK C 140.076760
100%
1.5BHK55.027270
100%
2BHK D65.9676760
100%
RETAIL SHOP 2146.0110
100%
STUDIO A 121.6555550
100%
STUDIO C27.1332320
100%

TOWER 5

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK39.48101
0%
1BHK J35.3404
0%
1RK21.46101
0%
1RK37.81101
0%
1RK46.63101
0%
2BHK A 263.7328622
21%
2BHK B64.7532329
9%
2BHK C66.2459752
12%
3BHK75.5368761
10%

TOWER 7

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK A 245.52681454
21%
1 BHK A 345.34371720
46%
1 BHK F 237.81681256
18%
1 BHK H39.86371423
38%
1 BHK K39.4831229
6%
1BHK65.21404
0%
STUDIO34.83505
0%
STUDIO A321.46683632
53%
STUDIO A421.37644519
70%

Construction Progress

TOWER 2

Basement (if any)0%
Excavation70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

TOWER 4

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

TOWER 5

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

TOWER 7

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

TOWER 8

Basement (if any)0%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

✅Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
✅Fire protection and fire safety requirements
✅GYM FITNESS CENTRE
✅Internal Roads & Footpaths
✅JOGGING TRACK
✅KIDS OUTDOOR PLAY AREA
✅KIDS POOL
✅Landscaping & Tree Planting
✅MULTIPURPOSE HALL
✅Open Parking
✅REFELEXOLOGY TRACK
✅SENIOR CITIZEN AREA
✅SKATING RINK
✅SWIMMING POOL
✅Sewerage (Chamber, Lines, Septic Tank , STP)
✅Solid Waste Management And Disposal
✅Storm Water Drains
✅Street Lighting
✅TODDLERS INDOOR PLAY ROOM
✅Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting

Latest Mumbai Property News

View all news →
CallWhatsApp
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now