Ankit Fiona Phase 2

by Mahesh Padalkar
Certificate SignedP52000018126
Ankit Fiona Phase 2Project photos will appear here when available.

Project Information

RERA Certificate No.
P52000018126
Registration No.
REA52000044855
Developer
Mahesh Padalkar
Project Bank
KOTAK MAHINDRA BANK LTD
Proposed Possession
2026-12-31
Revised Possession
1900-01-01
Extended Possession
2025-01-31
Total Units
28
Units Sold
0 (0%)
Buildings
1
Project Area
1686.31 sq.m
Total FSI
1686.30
MahaRERA QR
Ankit Fiona Phase 2
MahaRERA — P52000018126
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors6
✅Sanctioned6
🏠Habitable5
🔢Total Units28
🏡Residential28

Apartment Configurations

CORAL

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK TYPE 149.22404
0%
1 BHK TYPE 253.38404
0%
2 BHK TYPE 152.91101
0%
2 BHK TYPE 1067.49404
0%
2 BHK TYPE 1168.4202
0%
2 BHK TYPE 253.56101
0%
2 BHK TYPE 354.62101
0%
2 BHK TYPE 455.26101
0%
2 BHK TYPE 563.62202
0%
2 BHK TYPE 664.86202
0%
2 BHK TYPE 765.03202
0%
2 BHK TYPE 865.99202
0%
2 BHK TYPE 966.9202
0%

Construction Progress

CORAL

Basement (if any)80%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor60%

RERA Registered Amenities

✅Aggregate area of recreational Open Space
✅Community Buildings50%
✅Electrical meter room, sub-station, receiving station
✅Energy managemcnt
⬜Fire protection and fire safety requirements
✅Internal Roads & Footpaths50%
✅Landscaping & Tree Planting
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
✅Solid Waste Management And Disposal
✅Storm Water Drains
✅Street Lighting
✅Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting