RERA: A51800043517

ARAFAT CHS LTD,ANAB CHS LTD, AL ASHIYANA CHS LTD.

by KARARI GROUP BUILDERS & DEVELOPERS
Kept in AbeyanceP99000055168

Project Information

RERA Certificate No.
P99000055168
Developer
KARARI GROUP BUILDERS & DEVELOPERS
Project Bank
HDFC BANK LTD
Proposed Possession
2027-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Buildings
2
Project Area
2181.62 sq.m
Total FSI
10269.65
Approved FSI
3272.65
MahaRERA QR
ARAFAT CHS LTD,ANAB CHS LTD, AL ASHIYANA CHS LTD.
MahaRERA — P99000055168
Scan to verify on MahaRERA portal

Wing-wise Details

🚗Open Parking17
🅿️Closed Parking22
📅Completion2027-12-31

Apartment Configurations

Arafat Chs Ltd, Anab Chs Ltd, Al Ashiyana Chs Ltd

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK37.78606
0%
1 BHK37.8513013
0%
1RK26.28101
0%
1RK27.13101
0%
2 BHK47.7606
0%
2 BHK48.66707
0%
2 BHK53.9412012
0%
3 BHK61.8303
0%
3 BHK66.63101
0%
ExistingTenants.1 BHK37.7811011
0%
ExistingTenants.1bhk37.85606
0%
ExistingTenants.2 BHK47.712012
0%
ExistingTenants.2 BHK48.6610010
0%
ExistingTenants.2 BHK53.94606
0%
ExistingTenants.2bhk49.87808
0%
ExistingTenants.3bhk61.8606
0%

Construction Progress

Arafat Chs Ltd, Anab Chs Ltd, Al Ashiyana Chs Ltd

Excavation0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now