List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

ARIHANT 6 ANAIKA

by ARIHANT ENTERPRISES Partnership
Certificate SignedP52000031132
ARIHANT 6 ANAIKAProject photos will appear here when available.

Project Information

RERA Certificate No.
P52000031132
Registration No.
REA52000095009
Registration Date
2021-10-05
Developer
ARIHANT ENTERPRISES Partnership
Architect
YOGITA BHANDARKAR
Project Bank
ICICI BANK LIMITED
Proposed Possession
2027-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
267
Units Sold
248 (93%)
Buildings
2
Project Area
6210.00 sq.m
Total FSI
19397.60
Approved FSI
11824.34
MahaRERA QR
ARIHANT 6 ANAIKA
MahaRERA — P52000031132
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors15
✅Sanctioned15
🏠Habitable13
🔢Total Units127
🏡Residential127
🏗️Proposed Floors15
✅Sanctioned15
🏠Habitable13
🔢Total Units140
🏡Residential140

Apartment Configurations

U

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK32.1549490
100%
2BHK47.69786315
81%

V

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK32.1562620
100%
2BHK47.6978726
92%

Construction Progress

U

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises93%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

V

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.98%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises93%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

✅Aggregate area of recreational Open Space90%
✅Community Buildings100%
✅Electrical meter room, sub-station, receiving station100%
✅Energy managemcnt100%
✅Fire protection and fire safety requirements
✅Internal Roads & Footpaths100%
✅Landscaping & Tree Planting90%
✅Open Parking100%
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
✅Solid Waste Management And Disposal100%
✅Storm Water Drains100%
✅Street Lighting100%
✅Treatment And Disposal Of Sewage And Sullage Water100%
✅Water Supply100%
✅Water conservation /Rain water harvesting100%