RERA: A51800043517

Arihant Residency

by Aditya Deepak Karnawat Individual
Certificate SignedP99000032477

Project Information

RERA Certificate No.
P99000032477
Registration No.
REA99000093482
Registration Date
2022-01-04
Developer
Aditya Deepak Karnawat Individual
Architect
Narendra Sharma
Project Bank
HDFC BANK
Proposed Possession
2024-04-30
Revised Possession
1900-01-01
Extended Possession
2025-04-30
Units Sold
0
Buildings
4
Project Area
1398.00 sq.m
Total FSI
1372.95
Approved FSI
1372.95
MahaRERA QR
Arihant Residency
MahaRERA — P99000032477
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors3
Sanctioned3
📅Completion2024-04-30
🏗️Proposed Floors5
Sanctioned5
🅿️Closed Parking6
📅Completion2024-04-30
🏗️Proposed Floors3
Sanctioned3
📅Completion2024-04-30
📅Completion2024-04-30

Apartment Configurations

A - Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Comm and Resi543.321284
67%

B - Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK35.64101
0%
1 BHK40.36431
75%
1 BHK41.27211
50%
2 BHK63.03101
0%
3 BHK79.09110
100%
3 BHK84.01110
100%

C - Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1RK115.92624
33%

Not Applicable

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1RK000
0%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk35.63999938964844000
0%
1Bhk40.36000061035156000
0%
1Bhk41.27000045776367000
0%
1Rk000
0%
1Rk115.91999816894531000
0%
2Bhk63.029998779296875000
0%
3Bhk79.08999633789062000
0%
3Bhk84.01000213623047000
0%
Comm And Resi543.3200073242188000
0%

Construction Progress

A - WING

Basement (if any)0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth0%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

A - Wing

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate95%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure100%

B - WING

Basement (if any)0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth0%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

B - Wing

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate70%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises80%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing95%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure100%

C - WING

Basement (if any)100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

C - Wing

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing80%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Not Applicable

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises90%
Overall Percentage of Completion of the work done For the entire Building /Wing82%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises50%
Sanitary Fittings within the flats / premises50%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing90%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station100%
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking100%
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal100%
Storm Water Drains
Street Lighting70%
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting100%
Water Supply100%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now