Project Information
RERA Certificate No.
P51800005938
Registration No.
REA51800010768
Registration Date
2017-08-14
Developer
Devleela Developers Partnership
Architect
Tarun H Motta
Project Bank
ICICI BANK LIMITED
Proposed Possession
2019-12-31
Revised Possession
2019-12-31
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
1327.70 sq.m
Total FSI
3567.04
Approved FSI
3567.04
Ashara
MahaRERA — P51800005938
MahaRERA — P51800005938
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors20
✅Sanctioned20
Apartment Configurations
ASHARA
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| three bhk | 71.82 | 2 | 2 | 0 | 100% |
| three bhk | 77.9 | 1 | 1 | 0 | 100% |
| three bhk | 82.72 | 2 | 2 | 0 | 100% |
| three bhk | 87.29 | 2 | 2 | 0 | 100% |
| three bhk | 89.12 | 2 | 2 | 0 | 100% |
| three bhk | 91.16 | 6 | 5 | 1 | 83% |
| two bhk | 59.46 | 2 | 2 | 0 | 100% |
| two bhk | 61.38 | 2 | 1 | 1 | 50% |
| two bhk | 65.08 | 18 | 18 | 0 | 100% |
| two bhk | 72.64 | 2 | 0 | 2 | 0% |
| two bhk | 76.76 | 1 | 1 | 0 | 100% |
| two bhk | 51.78 | 4 | 2 | 2 | 50% |
Construction Progress
ASHARA
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
✅Fire protection and fire safety requirements50%
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting
✅Open Parking50%
✅Sewerage (Chamber, Lines, Septic Tank , STP)
⬜Solid Waste Management And Disposal
✅Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting10%