Bafna Meadows Phase 2

by Suvidha Realtors Partnership
Certificate SignedP99000002364
Bafna Meadows Phase 2Project photos will appear here when available.

Project Information

RERA Certificate No.
P99000002364
Registration No.
REA99000009358
Registration Date
2021-09-09
Developer
Suvidha Realtors Partnership
Architect
Sairachana
Project Bank
BANK OF BARODA
Proposed Possession
2023-06-30
Revised Possession
2022-12-01
Extended Possession
2023-06-30
Units Sold
0
Buildings
3
Project Area
5577.78 sq.m
Total FSI
6018.33
Approved FSI
6018.33
MahaRERA QR
Bafna Meadows Phase 2
MahaRERA — P99000002364
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors8
✅Sanctioned8
🏗️Proposed Floors8
✅Sanctioned8
🏗️Proposed Floors6
✅Sanctioned6

Apartment Configurations

Iris

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK38.2424195
79%
1BHK38.3818162
89%

Ivy

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK41.06660
100%
2BHK47.03202
0%
2BHK49.281248
33%
2BHK51.13651
83%
2BHK51.15660
100%

Tulip

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK44.41431
75%
1BHK46.85431
75%
2BHK50.28440
100%
2BHK54.47440
100%
2BHK59.05440
100%
2BHK61.14440
100%
SHOP10.75110
100%
SHOP12.31110
100%
SHOP13.87110
100%
SHOP13.91110
100%
SHOP15.43110
100%
SHOP16.8110
100%
SHOP17.46101
0%
SHOP18.47110
100%
SHOP23.33110
100%

Construction Progress

Iris

Basement (if any)80%
Excavation80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises13%
Plinth80%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure80%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks33%
Stilt Floor50%

Ivy

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Tulip

Basement (if any)100%
Excavation90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.68%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises57%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks57%
Stilt Floor60%

RERA Registered Amenities

✅Aggregate area of recreational Open Space
✅Community Buildings
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
✅Fire protection and fire safety requirements
✅Internal Roads & Footpaths50%
✅Landscaping & Tree Planting50%
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
⬜Solid Waste Management And Disposal
✅Storm Water Drains100%
✅Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply50%
✅Water conservation /Rain water harvesting