Project Information

RERA Certificate No.
P51700017923
Developer
Indo Asian Buildcon Pvt Ltd
Project Bank
AXIS BANK
Proposed Possession
2020-12-30
Revised Possession
1900-01-01
Extended Possession
2021-12-30
Total Units
32
Units Sold
22 (69%)
Project Area
12000.00 sq.m
Total FSI
6562.14
MahaRERA QR
Bella Vista Phase 8B
MahaRERA — P51700017923
Scan to verify on MahaRERA portal

Construction Progress

NA Plot Without Structure

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

Aggregate area of recreational Open Space50%
Community Buildings
Electrical meter room, sub-station, receiving station
Energy managemcnt
Fire protection and fire safety requirements
Internal Roads & Footpaths50%
Landscaping & Tree Planting50%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Supply10%
Water conservation /Rain water harvesting