BHAKTI ORNATEProject photos will appear here when available.
Project Information
RERA Certificate No.
P52000026522
Registration No.
REA52000076707
Registration Date
2021-09-08
Developer
SKYLINE INFRASTRUCTURE Partnership
Architect
Atul Patel Architects
Project Bank
AXIS BANK
Proposed Possession
2024-06-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
749.86 sq.m
Total FSI
1116.95
Approved FSI
1116.95
BHAKTI ORNATE
MahaRERA — P52000026522
MahaRERA — P52000026522
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors7
✅Sanctioned7
Apartment Configurations
BHAKTI ORNATE
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1BHK | 21.07 | 1 | 0 | 1 | 0% |
| 1BHK | 21.63 | 1 | 0 | 1 | 0% |
| 1BHK | 22.02 | 1 | 0 | 1 | 0% |
| 1BHK | 25.33 | 1 | 1 | 0 | 100% |
| 1BHK | 25.45 | 1 | 1 | 0 | 100% |
| 1BHK | 25.47 | 1 | 1 | 0 | 100% |
| 1BHK | 26.16 | 3 | 1 | 2 | 33% |
| 1BHK | 26.74 | 4 | 2 | 2 | 50% |
| 1BHK | 26.88 | 4 | 2 | 2 | 50% |
| 2BHK | 31.07 | 1 | 1 | 0 | 100% |
| 2BHK | 31.72 | 1 | 1 | 0 | 100% |
| 2BHK | 36.83 | 1 | 1 | 0 | 100% |
| 2BHK | 39.05 | 4 | 2 | 2 | 50% |
| 2BHK | 39.35 | 1 | 0 | 1 | 0% |
| 2BHK | 40.42 | 3 | 1 | 2 | 33% |
| 2BHK | 41.54 | 1 | 1 | 0 | 100% |
| Shop | 25.99 | 2 | 0 | 2 | 0% |
| Shop | 26.89 | 2 | 0 | 2 | 0% |
Construction Progress
BHAKTI ORNATE
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station100%
⬜Energy managemcnt
✅Fire protection and fire safety requirements100%
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting100%
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
⬜Solid Waste Management And Disposal
⬜Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply100%
✅Water conservation /Rain water harvesting100%