List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

BHAVESHWAR AQUA - 1

by BHAVESHWAR INFRATECH Partnership
Certificate SignedP52000079390
BHAVESHWAR AQUA - 1Project photos will appear here when available.

Project Information

RERA Certificate No.
P52000079390
Registration No.
REA52000167518
Registration Date
2025-03-03
Developer
BHAVESHWAR INFRATECH Partnership
Architect
ATUL PATEL ARCHITECTS
Project Bank
AXIS BANK
Proposed Possession
2030-04-30
Total Units
334
Units Sold
85 (25%)
Buildings
2
Project Area
3945.98 sq.m
Total FSI
24500.00
Approved FSI
18945.00
MahaRERA QR
BHAVESHWAR AQUA - 1
MahaRERA — P52000079390
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors17
✅Sanctioned17
🏠Habitable15
🔢Total Units184
🏡Residential156
🏢Non-Residential28
🏗️Proposed Floors16
✅Sanctioned16
🏠Habitable13
🔢Total Units150
🏡Residential150

Construction Progress

WING A

Basement (if any)60%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.3%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.16%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure17%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks9%
Stilt Floor50%

WING B

Basement (if any)60%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.3%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.16%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure17%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks9%
Stilt Floor50%

RERA Registered Amenities

✅Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
✅Fire protection and fire safety requirements
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)
⬜Solid Waste Management And Disposal
⬜Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting