BLOSSOM AVENUE

by DILIPKUMAR AMBALAL JAIN Individual
Certificate Signed P99000066574
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P99000066574
Registration No.
REA99000152760
Registration Date
2024-06-11
Developer
DILIPKUMAR AMBALAL JAIN Individual
Architect
Roshan Patil And Associates
Project Bank
HDFC BANK
Proposed Possession
2030-12-31
Units Sold
0
Project Area
10773.60 sq.m
Total FSI
16475.62
Approved FSI
16475.62
MahaRERA QR
BLOSSOM AVENUE
MahaRERA — P99000066574
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors3
Sanctioned3
🚗Open Parking24
🅿️Closed Parking1
📅Completion2030-12-31
🏗️Proposed Floors7
Sanctioned7
🚗Open Parking25
🅿️Closed Parking1
📅Completion2030-12-31
🏗️Proposed Floors7
Sanctioned7
🚗Open Parking26
🅿️Closed Parking1
📅Completion2030-12-31
🏗️Proposed Floors7
Sanctioned7
🚗Open Parking25
🅿️Closed Parking1
📅Completion2030-12-31
🏗️Proposed Floors6
Sanctioned6
🚗Open Parking19
🅿️Closed Parking1
📅Completion2030-12-31
🏗️Proposed Floors6
Sanctioned6
🚗Open Parking20
🅿️Closed Parking1
📅Completion2030-12-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
1Bhk 26.049999237060547 0 0 0
0%
1Bhk 30.780000686645508 0 0 0
0%
2Bhk 38.79999923706055 0 0 0
0%
Shop 44.599998474121094 0 0 0
0%
Shop 51.79999923706055 0 0 0
0%

Amenity Building

Type Carpet (sq.ft) Total Booked Available Status
Shop 44.6 10 0 10
0%
Shop 51.8 5 0 5
0%

Building N0 1 A And B Wing

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 26.05 36 0 36
0%
1 BHK 30.78 26 0 26
0%
2 BHK 38.8 14 0 14
0%

Building No 2 A And B Wing

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 26.05 36 0 36
0%
1 BHK 30.78 26 0 26
0%
2 BHK 38.8 14 0 14
0%

Building No 3 A And B Wing

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 26.05 36 0 36
0%
1 BHK 30.78 26 0 26
0%
2 BHK 38.8 14 0 14
0%

Building No 4 A And B Wing

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 26.05 30 0 30
0%
1 BHK 30.78 22 0 22
0%
2 BHK 38.8 12 0 12
0%

Building No 5 A And B Wing

Type Carpet (sq.ft) Total Booked Available Status
1 BHK 26.05 30 0 30
0%
1 BHK 30.78 22 0 22
0%
2 BHK 38.8 12 0 12
0%

Construction Progress

AMENITY BUILDING

Basement (if any)0%

Amenity Building

Excavation0%

AMENITY BUILDING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Amenity Building

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

AMENITY BUILDING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Amenity Building

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

AMENITY BUILDING

Plinth0%
Podiums (if any) 0%

Amenity Building

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

AMENITY BUILDING

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Amenity Building

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

AMENITY BUILDING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Amenity Building

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUILDING N0 1 A AND B WING

Basement (if any)100%

Building N0 1 A And B Wing

Excavation100%

BUILDING N0 1 A AND B WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Building N0 1 A And B Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUILDING N0 1 A AND B WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Building N0 1 A And B Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%

BUILDING N0 1 A AND B WING

Plinth100%
Podiums (if any) 0%

Building N0 1 A And B Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING N0 1 A AND B WING

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Building N0 1 A And B Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUILDING N0 1 A AND B WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Building N0 1 A And B Wing

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUILDING NO 2 A AND B WING

Basement (if any)0%

Building No 2 A And B Wing

Excavation0%

BUILDING NO 2 A AND B WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Building No 2 A And B Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUILDING NO 2 A AND B WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Building No 2 A And B Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

BUILDING NO 2 A AND B WING

Plinth0%
Podiums (if any) 0%

Building No 2 A And B Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING NO 2 A AND B WING

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Building No 2 A And B Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUILDING NO 2 A AND B WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Building No 2 A And B Wing

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUILDING NO 3 A AND B WING

Basement (if any)0%

Building No 3 A And B Wing

Excavation100%

BUILDING NO 3 A AND B WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Building No 3 A And B Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUILDING NO 3 A AND B WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Building No 3 A And B Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing10%

BUILDING NO 3 A AND B WING

Plinth0%
Podiums (if any) 0%

Building No 3 A And B Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING NO 3 A AND B WING

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Building No 3 A And B Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUILDING NO 3 A AND B WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Building No 3 A And B Wing

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUILDING NO 4 A AND B WING

Basement (if any)0%

Building No 4 A And B Wing

Excavation0%

BUILDING NO 4 A AND B WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Building No 4 A And B Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUILDING NO 4 A AND B WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Building No 4 A And B Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%

BUILDING NO 4 A AND B WING

Plinth0%
Podiums (if any) 0%

Building No 4 A And B Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING NO 4 A AND B WING

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Building No 4 A And B Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUILDING NO 4 A AND B WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Building No 4 A And B Wing

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

BUILDING NO 5 A AND B WING

Basement (if any)100%

Building No 5 A And B Wing

Excavation100%

BUILDING NO 5 A AND B WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Building No 5 A And B Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUILDING NO 5 A AND B WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Building No 5 A And B Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing20%

BUILDING NO 5 A AND B WING

Plinth100%
Podiums (if any) 0%

Building No 5 A And B Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING NO 5 A AND B WING

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Building No 5 A And B Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUILDING NO 5 A AND B WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Building No 5 A And B Wing

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.