Bramhandnayak by Swamini Infra

πŸ“ Shirgaon, Thane Β· 421503
68
Units
2028
Possession
1
Buildings
Certificate Signed
Status
01

Possession Timeline

Proposed
Dec 2028
Status
New
02

Unit Configurations (per MahaRERA)

ConfigurationCarpetIndicative Price
Shop80–175 ftΒ²On request
Landowner Office204 ftΒ²On request
1 BHK Landowner365–382 ftΒ²On request
1 BHK365–384 ftΒ²On request
2 BHK471–489 ftΒ²On request
2 BHK Landowner471–489 ftΒ²On request
Configurations & carpet per MahaRERA filing Β· indicative price = locality rate Γ— carpet (not the developer's quote).
πŸ’¬ Live availability, floor plans & today's price β€” on WhatsApp
03

RERA Trust Record

MahaRERA No.
P51700078848
Registered
2025-01-15
Litigation
None on record
Escrow Bank
KOTAK MAHINDRA BANK LIMITED
Architect
β€”
Total FSI
2715
04

Buildings Β· 1 Wing(s)

Bramhandnayak7 floors Β· β€” units
05

Land DNA Β· Genesis

Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06

Location

πŸ“ Shirgaon
0.000000000000000,0.000000000000000
β–Έ Explore map & Street View β€” for verified buyers
09

Construction Progress

0% avg
Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Plinth0%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
10

Amenities

Electrical Meter Room, Sub-Station, Receiving StationFire Protection And Fire Safety RequirementsOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsStreet LightingWater Conservation, Rain water HarvestingWater Supply
12

Floor Plans, E-Brochure & Payment Plans

πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13

EMI Calculator

β€”
15

MahaRERA projects nearby in Shirgaon

Mohan Willows Iii492 unitsTrident Vrindavan244 unitsKrishna Nayan Complex Phase I171 unitsShreeji Iconic161 unitsSatyam Sheela Wing F141 unitsVed Heights140 unitsShreeji Landmark Nx140 unitsShubh Vinayak Savarkar129 unitsPARIJATAK PHASE I A AND B WING128 unitsShivshakti Oasis121 unitsShubh Vastu Phase Iii112 unitsShreeji Landmark Phase Ii111 units
?

Frequently Asked Questions

When is possession of Bramhandnayak?

As per MahaRERA, proposed possession is Dec 2028.

Is Bramhandnayak RERA-registered?

Yes β€” MahaRERA registration P51700078848, registered 2025-01-15. No litigations on record.

Who is the developer?

Swamini Infra β€” 1 projects tracked on Mumbai Property Exchange. View their track record β–Έ

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Shirgaon β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
Our advisor replies on WhatsApp within 2 working hours (9am–8pm IST).
βœ“ MahaRERA P51900079270β˜… Featured
Runwal Enterprises
7 Mahalaxmi, Mahalaxmi
2 BHK, 3 BHK, 4 BHK Β· β‚Ή56,000/sq.ft Β· Possession Dec 2031
Learn more β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’