Brooklyn ApartmentsProject photos will appear here when available.
Project Information
RERA Certificate No.
P51900004241
Registration No.
REA51900015418
Registration Date
2017-08-09
Developer
Sahajanand Enterprises Partnership
Architect
Jasleen Kaur Milind Changani
Project Bank
HDFC BANK
Proposed Possession
2017-12-31
Revised Possession
2017-12-31
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
488.30 sq.m
Total FSI
1550.36
Approved FSI
1550.36
Brooklyn Apartments
MahaRERA — P51900004241
MahaRERA — P51900004241
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors18
✅Sanctioned18
Apartment Configurations
BROOKLYN APARTMENTS
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1RK | 27.88 | 1 | 1 | 0 | 100% |
| 1RK | 30.8 | 1 | 1 | 0 | 100% |
| 2BHK | 72.97 | 1 | 1 | 0 | 100% |
| 2BHK | 73.54 | 1 | 1 | 0 | 100% |
| 2BHK | 76.95 | 1 | 1 | 0 | 100% |
| 3BHK | 83.28 | 1 | 1 | 0 | 100% |
| 3BHK | 104.0 | 8 | 8 | 0 | 100% |
| 3BHK | 150.49 | 1 | 1 | 0 | 100% |
Construction Progress
BROOKLYN APARTMENTS
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station100%
⬜Energy managemcnt
✅Fire protection and fire safety requirements100%
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting100%
✅Open Parking90%
✅Sewerage (Chamber, Lines, Septic Tank , STP)90%
⬜Solid Waste Management And Disposal
✅Storm Water Drains90%
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply100%
✅Water conservation /Rain water harvesting100%