Burhani BuildingProject photos will appear here when available.
Project Information
RERA Certificate No.
P51800003165
Registration No.
REA51800007574
Registration Date
2020-06-11
Developer
Ms Developers Partnership
Architect
A R Metha & Associates
Proposed Possession
2020-12-30
Revised Possession
2020-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
2775.78 sq.m
Total FSI
3688.42
Approved FSI
3688.42
Burhani Building
MahaRERA — P51800003165
MahaRERA — P51800003165
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors13
✅Sanctioned13
Apartment Configurations
BURHANI BUILDING
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| FLAT | 23.34 | 9 | 8 | 1 | 89% |
| FLAT | 27.0 | 3 | 2 | 1 | 67% |
| FLAT | 32.84 | 12 | 10 | 2 | 83% |
| FLAT | 33.06 | 68 | 61 | 7 | 90% |
| OFFICE | 64.38 | 1 | 0 | 1 | 0% |
| OFFICE | 66.48 | 1 | 0 | 1 | 0% |
| SHOP | 19.79 | 6 | 4 | 2 | 67% |
| SHOP | 20.14 | 1 | 1 | 0 | 100% |
| SHOP | 20.39 | 1 | 1 | 0 | 100% |
| SHOP | 20.81 | 1 | 1 | 0 | 100% |
| SHOP | 20.86 | 2 | 2 | 0 | 100% |
| SHOP | 21.07 | 1 | 1 | 0 | 100% |
Construction Progress
BURHANI BUILDING
RERA Registered Amenities
✅Aggregate area of recreational Open Space100%
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station100%
⬜Energy managemcnt
✅Fire protection and fire safety requirements100%
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting100%
✅Open Parking100%
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
⬜Solid Waste Management And Disposal
✅Storm Water Drains100%
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply100%
✅Water conservation /Rain water harvesting100%