Chandrangan Residency Phase - IiProject photos will appear here when available.
Project Information
RERA Certificate No.
P51700025153
Developer
Ekveera Enterprises
Architect
Joshi Deshaware &Amp; Associates
Project Bank
THE BHARAT CO-OP BANK LTD
Proposed Possession
2023-12-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
3
Project Area
3454.93 sq.m
Total FSI
7452.47
Chandrangan Residency Phase - Ii
MahaRERA — P51700025153
MahaRERA — P51700025153
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors22
✅Sanctioned22
🏗️Proposed Floors22
✅Sanctioned22
🏗️Proposed Floors4
✅Sanctioned4
Apartment Configurations
BUILDING - A
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1BHK | 31.95 | 49 | 49 | 0 | 100% |
| 1BHK | 32.74 | 17 | 5 | 12 | 29% |
| 1BHK | 33.44 | 5 | 5 | 0 | 100% |
| 1BHK | 34.44 | 2 | 2 | 0 | 100% |
| 1BHK | 34.73 | 17 | 3 | 14 | 18% |
| 1BHK | 35.57 | 3 | 3 | 0 | 100% |
| 1BHK | 36.67 | 3 | 3 | 0 | 100% |
| 2BHK | 42.96 | 1 | 1 | 0 | 100% |
| 2BHK | 44.54 | 17 | 4 | 13 | 24% |
| 2BHK | 46.63 | 3 | 3 | 0 | 100% |
BUILDING - B
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1BHK | 32.31 | 14 | 8 | 6 | 57% |
| 1BHK | 32.32 | 37 | 19 | 18 | 51% |
| 1BHK | 34.29 | 3 | 0 | 3 | 0% |
| 1BHK | 34.33 | 6 | 0 | 6 | 0% |
| 2BHK | 44.8 | 17 | 6 | 11 | 35% |
| 2BHK | 44.81 | 1 | 1 | 0 | 100% |
| 2BHK | 45.42 | 18 | 9 | 9 | 50% |
| 2BHK | 47.02 | 3 | 0 | 3 | 0% |
| 2BHK | 47.18 | 3 | 0 | 3 | 0% |
| Office space | 35.31 | 1 | 0 | 1 | 0% |
| Office space | 37.0 | 2 | 0 | 2 | 0% |
| Shop | 34.15 | 1 | 0 | 1 | 0% |
| Shop | 35.92 | 1 | 0 | 1 | 0% |
| Shop | 37.0 | 2 | 0 | 2 | 0% |
| Shop | 68.5 | 1 | 0 | 1 | 0% |
BUILDING - C
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| Bungalow | 467.04 | 1 | 0 | 1 | 0% |
Construction Progress
BUILDING - A
BUILDING - B
BUILDING - C
RERA Registered Amenities
⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅DG Set Installation100%
✅Electrical meter room, sub-station, receiving station100%
⬜Energy managemcnt
⬜Fire protection and fire safety requirements
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting100%
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
✅Solar Panel Installation100%
⬜Solid Waste Management And Disposal
✅Storm Water Drains100%
⬜Street Lighting
✅Treatment And Disposal Of Sewage And Sullage Water100%
✅Water Supply100%
✅Water conservation /Rain water harvesting100%