Chandrangan Residency Phase-Iv

by Ekveera Enterprises
Certificate SignedP51700056036
Chandrangan Residency Phase-IvProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700056036
Registration No.
REA51700152987
Registration Date
2024-05-10
Developer
Ekveera Enterprises
Architect
Joshi Deshaware & Associates
Project Bank
BHARAT COOPERATIVE BANK MUMBAI LIMITED
Proposed Possession
2027-04-30
Units Sold
0
Buildings
2
Project Area
3283.83 sq.m
Total FSI
2195.58
Approved FSI
2195.58
MahaRERA QR
Chandrangan Residency Phase-Iv
MahaRERA — P51700056036
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors21
✅Sanctioned21
🏗️Proposed Floors2
✅Sanctioned2

Apartment Configurations

BUILDING A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK Landowner29.86404
0%
1 BHK Landowner29.8926026
0%
1BHK29.8614410
29%
1BHK29.891006535
65%
2 BHK Landowner51.53606
0%
2 BHK Landowner58.74909
0%
2BHK51.53361125
31%
2BHK58.7431625
19%

BUNGALOW

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow278.1101
0%

Construction Progress

BUILDING A

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises14%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor100%

BUNGALOW

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅D G SET INSTALLATION
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
✅Fire protection and fire safety requirements
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting
⬜Open Parking
✅SOLAR PANEL INSTALLATION
✅Sewerage (Chamber, Lines, Septic Tank , STP)
⬜Solid Waste Management And Disposal
✅Storm Water Drains
⬜Street Lighting
✅TRANSFORMER
✅Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting

Latest Mumbai Property News