Construction Of 69 Shops At Sno 263 Cts No 6A/6 Ekta Nagar Malwani Malad West Mumbai95

by Mumbai Housing And Area Development Board Public Authority
Certificate SignedP51800000026
Construction Of 69 Shops At Sno 263 Cts No 6A/6 Ekta Nagar Malwani Malad West Mumbai95Project photos will appear here when available.

Project Information

RERA Certificate No.
P51800000026
Registration No.
REA51800001463
Registration Date
2017-06-13
Developer
Mumbai Housing And Area Development Board Public Authority
Architect
Nitin Patil
Proposed Possession
2020-10-30
Revised Possession
2018-03-31
Extended Possession
2020-10-30
Units Sold
0
Buildings
3
Project Area
1804.17 sq.m
Total FSI
1804.17
Approved FSI
1804.17
MahaRERA QR
Construction Of 69 Shops At Sno 263 Cts No 6A/6 Ekta Nagar Malwani Malad West Mumbai95
MahaRERA — P51800000026
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors3
✅Sanctioned3
🏗️Proposed Floors3
✅Sanctioned3
🏗️Proposed Floors3
✅Sanctioned3

Apartment Configurations

BLDG NO 61

TypeCarpet (sq.ft)TotalBookedAvailableStatus
OFFICES14.1312012
0%
SHOPS14.13606
0%

BLDG NO 62

TypeCarpet (sq.ft)TotalBookedAvailableStatus
OFFICES11.4410010
0%
SHOPS11.44505
0%

BLDG NO 63

TypeCarpet (sq.ft)TotalBookedAvailableStatus
OFFICES12.2524024
0%
SHOPS12.2512012
0%

Construction Progress

BLDG NO 61

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

BLDG NO 62

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

BLDG NO 63

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station100%
✅Energy managemcnt
✅Fire protection and fire safety requirements
✅Internal Roads & Footpaths100%
✅Landscaping & Tree Planting90%
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
⬜Solid Waste Management And Disposal
✅Storm Water Drains100%
✅Street Lighting100%
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply90%
✅Water conservation /Rain water harvesting