List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

CRD Gardenia Apartments 2 - Phase III

by Dr Chandrashekhar Raghunath Dound Individual
Certificate SignedP99000049393
CRD Gardenia Apartments 2 - Phase IIIProject photos will appear here when available.

Project Information

RERA Certificate No.
P99000049393
Registration No.
REA99000128456
Registration Date
2023-02-08
Developer
Dr Chandrashekhar Raghunath Dound Individual
Architect
Trupti Jadhav
Project Bank
BANK OF MAHARASHTRA
Proposed Possession
2023-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
2
Project Area
11900.00 sq.m
Total FSI
235.40
Approved FSI
235.40
MahaRERA QR
CRD Gardenia Apartments 2 - Phase III
MahaRERA — P99000049393
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors1
✅Sanctioned1
🏗️Proposed Floors1
✅Sanctioned1

Apartment Configurations

Wing A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK Terrace38.61220
100%

Wing B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK Terrace38.61220
100%

Construction Progress

Wing A

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

Wing B

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

RERA Registered Amenities

✅Aggregate area of recreational Open Space80%
✅Community Buildings95%
✅Electrical meter room, sub-station, receiving station80%
⬜Energy managemcnt
⬜Fire protection and fire safety requirements
✅Internal Roads & Footpaths80%
✅Landscaping & Tree Planting80%
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)80%
⬜Solid Waste Management And Disposal
✅Storm Water Drains80%
✅Street Lighting80%
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply80%
✅Water conservation /Rain water harvesting80%