CRD Gardenia Apartments 4 - Phase II
by Dr Chandrashekhar Raghunath Dound
CRD Gardenia Apartments 4 - Phase IIProject photos will appear here when available.
Project Information
RERA Certificate No.
P99000019668
Registration No.
REA99000050887
Developer
Dr Chandrashekhar Raghunath Dound
Project Bank
ICICI BANK LTD
Proposed Possession
2031-04-30
Revised Possession
1900-01-01
Extended Possession
2024-12-29
Total Units
52
Units Sold
0 (0%)
Buildings
3
Project Area
1868.02 sq.m
Total FSI
3474.97
CRD Gardenia Apartments 4 - Phase II
MahaRERA — P99000019668
MahaRERA — P99000019668
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors1
✅Sanctioned1
🏠Habitable1
🔢Total
Units5
🏢Non-Residential5
🏗️Proposed Floors8
✅Sanctioned8
🏠Habitable8
🔢Total
Units47
🏡Residential47
Apartment Configurations
Podium
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| SHOP | 9.59 | 5 | 0 | 5 | 0% |
Wing A
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1BHK | — | 0 | 0 | 0 | 0% |
Wing B
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1BHK | 44.47 | 2 | 0 | 2 | 0% |
| 1BHK | 44.74 | 1 | 0 | 1 | 0% |
| 1BHK | 47.05 | 2 | 0 | 2 | 0% |
| 1BHK Deck | 39.82 | 14 | 0 | 14 | 0% |
| 1BHK Deck | 47.05 | 14 | 0 | 14 | 0% |
| 2BHK | 61.47 | 1 | 0 | 1 | 0% |
| 2BHK Deck | 61.45 | 6 | 0 | 6 | 0% |
| 2BHK Deck | 61.47 | 6 | 0 | 6 | 0% |
| 4BHK Deck | 111.32 | 1 | 0 | 1 | 0% |
Construction Progress
Podium
Wing A
Wing B
RERA Registered Amenities
✅Aggregate area of recreational Open Space80%
✅Community Buildings95%
✅Electrical meter room, sub-station, receiving station80%
⬜Energy managemcnt
⬜Fire protection and fire safety requirements
✅Internal Roads & Footpaths80%
✅Landscaping & Tree Planting80%
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)80%
⬜Solid Waste Management And Disposal
✅Storm Water Drains80%
✅Street Lighting80%
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply80%
✅Water conservation /Rain water harvesting80%