CRD Gardenia Apartments 6 - Phase III
by Dr Chandrashekhar Raghunath Dound
Individual
Project Information
RERA Certificate No.
P99000049411
Registration No.
REA99000128458
Registration Date
2023-02-08
Developer
Dr Chandrashekhar Raghunath Dound Individual
Architect
Trupti Jadhav
Project Bank
BANK OF MAHARASHTRA
Proposed Possession
2023-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
2
Project Area
11900.00 sq.m
Total FSI
235.40
Approved FSI
235.40
CRD Gardenia Apartments 6 - Phase III
MahaRERA — P99000049411
MahaRERA — P99000049411
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors1
✅Sanctioned1
📅Completion2023-12-31
🏗️Proposed Floors1
✅Sanctioned1
📅Completion2023-12-31
Apartment Configurations
Wing A
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK Terrace | 38.61 | 2 | 2 | 0 | 100% |
Wing B
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1 BHK Terrace | 38.61 | 2 | 2 | 0 | 100% |
None
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1Bhk Terrace | 38.61000061035156 | 0 | 0 | 0 | 0% |
Construction Progress
Wing A
Wing B
RERA Registered Amenities
✅Aggregate area of recreational Open Space80%
✅Community Buildings95%
✅Electrical Meter Room, Sub-Station, Receiving Station80%
⬜Energy management
⬜Fire Protection And Fire Safety
Requirements
✅Landscaping & Tree Planting80%
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)80%
⬜Solid Waste Management And Disposal
✅Storm Water Drains80%
✅Street Lighting80%
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Conservation, Rain water Harvesting80%
✅Water Supply80%