Crystal Builders And Developers

by Crystal Builders And Developers Partnership
Certificate SignedP51700047809
Crystal Builders And DevelopersProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700047809
Registration No.
REA51700115835
Registration Date
2023-04-13
Developer
Crystal Builders And Developers Partnership
Architect
Shirish G Nachane
Project Bank
THE KALYAN JANATA SAHAKARI BANK LTD.
Proposed Possession
2025-05-13
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
420.00 sq.m
Total FSI
1296.74
Approved FSI
1296.74
MahaRERA QR
Crystal Builders And Developers
MahaRERA — P51700047809
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors7
✅Sanctioned7

Apartment Configurations

Crystal Builders and Developers

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK38.56770
100%
2BHK53.0614140
100%
Shop5.88220
100%
Shop8.12110
100%

Construction Progress

Crystal Builders and Developers

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station100%
⬜Energy managemcnt
✅Fire protection and fire safety requirements100%
⬜Internal Roads & Footpaths
⬜Landscaping & Tree Planting
✅Open Parking100%
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
✅Solid Waste Management And Disposal100%
⬜Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply100%
⬜Water conservation /Rain water harvesting