Crystal Residency

by Sai Crystal Homes
Certificate SignedP99000047067
Crystal ResidencyProject photos will appear here when available.

Project Information

RERA Certificate No.
P99000047067
Developer
Sai Crystal Homes
Project Bank
Bassein Catholic Co op Bank Ltd
Proposed Possession
2024-12-30
Revised Possession
1900-01-01
Extended Possession
2024-12-30
Units Sold
0
Buildings
4
Project Area
3769.15 sq.m
Total FSI
1235.36
MahaRERA QR
Crystal Residency
MahaRERA — P99000047067
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors4
✅Sanctioned4
🏗️Proposed Floors4
✅Sanctioned4
🏗️Proposed Floors4
✅Sanctioned4
🏗️Proposed Floors4
✅Sanctioned4

Apartment Configurations

A Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK30.61220
100%
1BHK30.85110
100%
1BHK32.2110
100%

B Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK30.61220
100%
1BHK30.85110
100%
1BHK32.2101
0%

C Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK30.1330
100%
1BHK30.61651
83%
1BHK30.85110
100%
1BHK32.2220
100%

D Wing

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK30.1330
100%
1BHK30.61550
100%
1BHK30.85101
0%
1BHK32.2220
100%

Construction Progress

A Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

B Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

C Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

D Wing

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station100%
✅Energy managemcnt
⬜Fire protection and fire safety requirements
⬜Internal Roads & Footpaths
✅Landscaping & Tree Planting90%
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
⬜Solid Waste Management And Disposal
✅Storm Water Drains100%
✅Street Lighting100%
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting50%