Datta Prayag Apartment

by Milind Dattatraya Mavle Individual
Certificate SignedP99000007660

Project Information

RERA Certificate No.
P99000007660
Registration No.
REA99000014140
Registration Date
2017-08-17
Developer
Milind Dattatraya Mavle Individual
Architect
Nandadeep M Kokane & Associates
Proposed Possession
2018-06-30
Revised Possession
2018-06-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
636.30 sq.m
Total FSI
950.62
Approved FSI
950.62
MahaRERA QR
Datta Prayag Apartment
MahaRERA — P99000007660
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors5
Sanctioned5
📅Completion1900-01-01

Apartment Configurations

Datta Prayag

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK38.68101
0%
1 BHK40.37211
50%
1 BHK40.88211
50%
1 BHK43.24431
75%
2 BHK66.81624
33%

None

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1Bhk38.68000030517578000
0%
1Bhk40.369998931884766000
0%
1Bhk40.880001068115234000
0%
1Bhk43.2400016784668000
0%
2Bhk66.80999755859375000
0%

Construction Progress

Datta Prayag

Basement (if any)0%
Excavation95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises50%
Plinth0%
Podiums (if any) 0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises20%
Sanitary Fittings within the flats / premises20%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.50%
Stilt Floor50%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing50%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now