Deepanjali Chs Ltd. by Avaas Malhar Developers

Avaas Malhar Developers
πŸ“ Nilemore, Palghar Β· 401203
94
Units
2026
Possession
2
Buildings
Certificate Signed
Status
01

Possession Timeline

Proposed
Dec 2026
Status
New
02

Unit Configurations (per MahaRERA)

ConfigurationCarpetIndicative Price
Shop148–224 ftΒ²On request
1 BHK Allot Tenant307–322 ftΒ²On request
1 BHK307–322 ftΒ²On request
2 BHK Allot Tenant323–525 ftΒ²On request
2 BHK409–525 ftΒ²On request
Configurations & carpet per MahaRERA filing Β· indicative price = locality rate Γ— carpet (not the developer's quote).
πŸ’¬ Live availability, floor plans & today's price β€” on WhatsApp
03

RERA Trust Record

MahaRERA No.
P99000056486
Registered
2024-06-05
Litigation
None on record
Escrow Bank
DOMBIVLI NAGARI SAHAKARI BANK LIMITED
Architect
Umesh Kekre
Total FSI
4635
04

Buildings Β· 2 Wing(s)

Building No 18 floors Β· β€” units
Building No 28 floors Β· β€” units
05

Land DNA Β· Genesis

Redevelopment / SRA / MHADA / MMRDA / Freehold β€” provenance from MPE's verification layer. The genesis no portal shows.
06

Location

πŸ“ Nilemore
β–Έ Explore map & Street View β€” for verified buyers
07

Promoter & Professionals

AVNISH PARASNATH MISHRAPartner
KIRAN ANANT THAKURPartner
NAYAN NANDKUMAR JAINPartner
SAIDHNYA SACHIN PANDITPartner
09

Construction Progress

49% avg
Basement (if any)100%
Excavation100%
Plinth100%
Stilt Floor100%
X number of Basement(s) and Plinth100%
Excavation50%
Slabs of Super Structure50%
X number of Slabs of Super Structure50%
Overall Percentage of Completion of the work done For the entire Building /Wing35%
Overall Percentage of Completion of the work done For the entire Building /Wing5%
Basement (if any)0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
10

Amenities

Electrical Meter Room, Sub-Station, Receiving StationLandscaping & Tree PlantingOpen ParkingSewerage (Chamber, Lines, Septic Tank , STP)Storm Water DrainsStreet LightingWater Conservation, Rain water HarvestingWater Supply
12

Floor Plans, E-Brochure & Payment Plans

πŸ“ Unit floor plansπŸ“„ Official e-brochureπŸ’³ Payment plans Β· 20:80 Β· subvention Β· current offers

Shared on WhatsApp by our MahaRERA advisor β€” including the latest builder offers and payment schemes we don't list publicly.

πŸ’¬ Get floor plan, brochure & offers on WhatsApp
13

EMI Calculator

β€”
15

MahaRERA projects nearby in Nilemore

RUCHITA BLISS250 unitsELITE TOWER218 unitsSAI LEELA149 unitsVIMAL'S RAMJANKI CHSL131 unitsSAI NIDHI CO OPERATIVE HOUSING SOCIETY LIMITED (DEEP CROWN)90 unitsJIVDANI MATA CO-OPERATIVE HOUSING SOCIETY LTD70 unitsAASHIRWAD VRUNDAVAN63 unitsRUTURAJ CLASSICRadha HeightsCLOUDBERRYSAMVED ARCADEDEEP GARDEN 2
?

Frequently Asked Questions

When is possession of DEEPANJALI CHS LTD.?

As per MahaRERA, proposed possession is Dec 2026.

Is DEEPANJALI CHS LTD. RERA-registered?

Yes β€” MahaRERA registration P99000056486, registered 2024-06-05. No litigations on record.

Who is the developer?

Avaas Malhar Developers

How do I book or get more details?

Tap WhatsApp or Call below to speak with a Mumbai Property Exchange advisor β€” serving Mumbai since 1995 Β· RERA-registered since 2017.

SOURCE Β· MAHARERA + MUMBAI PROPERTY EXCHANGE
INDEPENDENT DATA Β· RERA A51800043517 Β· EST. 1995
WhatsAppEnquire β–Έ
🎯 AI Matchmaker
Tell us what you want in Nilemore β€” get matched
RERA-verified options on WhatsApp. No spam, no fakes.
Our advisor replies on WhatsApp within 2 working hours (9am–8pm IST).
βœ“ MahaRERA P51900006299β˜… Featured
Godrej Properties
Godrej Avenue Eleven B, Mahalaxmi
4 BHK Β· β‚Ή69,000/sq.ft Β· Possession Jan 2029
Learn more β€Ί

πŸ“° Latest Mumbai Property News

View all news β†’