DHULEVA ONE50

by THE NEW ERA AGENCIES PVT LTD Company
Certificate SignedPM1170002502807
DHULEVA ONE50Project photos will appear here when available.

Project Information

RERA Certificate No.
PM1170002502807
Registration No.
PM1170002502807
Registration Date
2026-03-16
Developer
THE NEW ERA AGENCIES PVT LTD Company
Proposed Possession
2034-04-30
Revised Possession
2033-12-31
Total Units
48
Units Sold
0 (0%)
Buildings
1
Project Area
18616.42 sq.m
MahaRERA QR
DHULEVA ONE50
MahaRERA — PM1170002502807
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors60
Sanctioned60
🏠Habitable39
🔢Total Units46
🏡Residential46
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units2
🏢Non-Residential2

Construction Progress

DHULEVA ONE50 - A Wing

Basement (if any)0%
Excavation3%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

DHULEVA ONE50 - B Wing

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical meter room, sub-station, receiving station
Energy managemcnt
Fire protection and fire safety requirements
Internal Roads & Footpaths
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Supply
Water conservation /Rain water harvesting