DIVINE ORCHID

by DELIGHT REALTORS Partnership
Certificate SignedP99000078647

Project Information

RERA Certificate No.
P99000078647
Registration No.
REA99000165768
Registration Date
2024-12-30
Developer
DELIGHT REALTORS Partnership
Architect
Umesh
Project Bank
HDFC BANK
Proposed Possession
2028-05-31
Units Sold
0
Project Area
4050.00 sq.m
Total FSI
14497.56
Approved FSI
9099.14
MahaRERA QR
DIVINE ORCHID
MahaRERA — P99000078647
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors3
Sanctioned3
🏠Habitable3
🚗Open Parking116
📅Completion2028-05-31
🏗️Proposed Floors12
Sanctioned12
🏠Habitable9
🚗Open Parking91
📅Completion2028-05-31
🏗️Proposed Floors12
Sanctioned12
🏠Habitable9
🚗Open Parking91
📅Completion2028-05-31

Apartment Configurations

Shops And Commercial Units

TypeCarpet (sq.ft)TotalBookedAvailableStatus
COMMERCIAL UNITS26.92202
0%
COMMERCIAL UNITS32.44202
0%
COMMERCIAL UNITS34.37202
0%
COMMERCIAL UNITS38.34202
0%
COMMERCIAL UNITS41.2202
0%
COMMERCIAL UNITS43.28202
0%
COMMERCIAL UNITS45.35202
0%
COMMERCIAL UNITS45.79202
0%
COMMERCIAL UNITS85.83202
0%
COMMERCIAL UNITS181.32101
0%
COMMERCIAL UNITS183.69101
0%
Shop33.3101
0%
Shop38.84101
0%
Shop42.54101
0%
Shop49.31101
0%
Shop50.66101
0%
Shop54.19101
0%
Shop54.2101
0%
Shop58.1101
0%
Shop85.57101
0%
Shop173.77101
0%

Wing - A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK59.4808
0%
2 BHK63.22808
0%
2 BHK64.17101
0%
3 BHK79.39808
0%
3 BHK81.73707
0%

Wing - B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2 BHK59.4808
0%
2 BHK63.22909
0%
2 BHK64.17101
0%
3 BHK79.39808
0%
3 BHK81.73707
0%

Construction Progress

SHOPS AND COMMERCIAL UNITS

Basement (if any)100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Shops And Commercial Units

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises20%
Overall Percentage of Completion of the work done For the entire Building /Wing42%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

WING - A

Basement (if any)100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure16%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

WING - B

Basement (if any)100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any) 0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure16%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Wing - A

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure16%

Wing - B

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure16%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now