Project Information

RERA Certificate No.
P52000029533
Registration No.
REA52000088122
Registration Date
2021-06-04
Developer
GREEN PARK DEVELOPERS Partnership
Architect
Abhijit Mohite
Project Bank
STATE BANK OF INDIA
Proposed Possession
2026-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
6
Project Area
3368.13 sq.m
Total FSI
1513.00
Approved FSI
1513.00
MahaRERA QR
EKAANTE PHASE 3
MahaRERA — P52000029533
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors1
✅Sanctioned1
🏗️Proposed Floors1
✅Sanctioned1
🏗️Proposed Floors1
✅Sanctioned1
🏗️Proposed Floors1
✅Sanctioned1
🏗️Proposed Floors1
✅Sanctioned1
🏗️Proposed Floors1
✅Sanctioned1

Apartment Configurations

0

TypeCarpet (sq.ft)TotalBookedAvailableStatus
0—000
0%

D3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
B3169.5110
100%

D4

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Type A15194.4110
100%

D5

TypeCarpet (sq.ft)TotalBookedAvailableStatus
B3169.5110
100%

D6

TypeCarpet (sq.ft)TotalBookedAvailableStatus
A3201.0110
100%

D7

TypeCarpet (sq.ft)TotalBookedAvailableStatus
A3201.0110
100%

Construction Progress

0

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

D3

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

D4

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

D5

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

D6

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

D7

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor0%

RERA Registered Amenities

✅Aggregate area of recreational Open Space50%
✅Community Buildings100%
✅Electrical meter room, sub-station, receiving station100%
⬜Energy managemcnt
⬜Fire protection and fire safety requirements
✅Internal Roads & Footpaths100%
⬜Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
⬜Solid Waste Management And Disposal
✅Storm Water Drains100%
✅Street Lighting100%
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply100%
✅Water conservation /Rain water harvesting100%