Eknath Enclave Building No 2

by Gaurivinayak Builders And Developers Pvt Ltd
Certificate SignedP51700033989
Eknath Enclave Building No 2Project photos will appear here when available.

Project Information

RERA Certificate No.
P51700033989
Registration No.
REA51700101217
Developer
Gaurivinayak Builders And Developers Pvt Ltd
Project Bank
CENTRAL BANK OF INDIA
Proposed Possession
2023-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
2
Project Area
3960.00 sq.m
Total FSI
1690.00
MahaRERA QR
Eknath Enclave Building No 2
MahaRERA — P51700033989
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors8
✅Sanctioned8
🏗️Proposed Floors3
✅Sanctioned3

Apartment Configurations

BUILDING NO 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK15.75808
0%
1RK12.1516016
0%
1RK14.1572072
0%

BUILDING NO 3 BUNGALOW

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Bungalow350.33101
0%

Construction Progress

BUILDING NO 2

Basement (if any)1%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Plinth1%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure8%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

BUILDING NO 3 BUNGALOW

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure2%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor100%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
⬜Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
✅Fire protection and fire safety requirements
⬜Internal Roads & Footpaths
⬜Landscaping & Tree Planting
✅Open Parking
⬜Sewerage (Chamber, Lines, Septic Tank , STP)
⬜Solid Waste Management And Disposal
⬜Storm Water Drains
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
⬜Water conservation /Rain water harvesting