ELEMENTS

by MAYUR VAN CLUB AND HOLIDAY RESORTS PRIVATE LIMITED Company
Certificate SignedP99000054499
ELEMENTSProject photos will appear here when available.

Project Information

RERA Certificate No.
P99000054499
Registration No.
REA99000148828
Registration Date
2024-01-25
Developer
MAYUR VAN CLUB AND HOLIDAY RESORTS PRIVATE LIMITED Company
Architect
Nishant Patil
Project Bank
IDBI BANK
Proposed Possession
2027-04-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
126
Units Sold
14 (11%)
Buildings
14
Project Area
11248.00 sq.m
Total FSI
9600.49
Approved FSI
9600.49
MahaRERA QR
ELEMENTS
MahaRERA — P99000054499
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors6
Sanctioned6
🏠Habitable6
🔢Total Units105
🏡Residential105
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units2
🏡Residential2
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units4
🏡Residential4
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units2
🏡Residential2
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units2
🏡Residential2
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units2
🏡Residential2
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units2
🏡Residential2
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units2
🏡Residential2
🏗️Proposed Floors2
Sanctioned2
🏠Habitable2
🔢Total Units1
🏡Residential1

Apartment Configurations

Building No 1 Type C and C1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK34.021050105
0%

Building No 10 Type D

TypeCarpet (sq.ft)TotalBookedAvailableStatus
5BHK224.77101
0%

Building No 11 Type D1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK181.79101
0%

Building No 12 Type A1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK129.78101
0%

Building No 13 Type A and A1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK129.78202
0%

Building No 14 Type A and A1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK129.78202
0%

Building No 15 Type A and A1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK129.78202
0%

Building No 16 Type A and A1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK129.78202
0%

Building No 3 Type B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
4BHK201.1101
0%

Building No 5 Type A and A1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK129.78202
0%

Building No 6 Type A and A1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK129.78202
0%

Building No 7 Type A and A1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK129.78202
0%

Building No 8 Type A and A1

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK129.78202
0%

Building No 9 Type A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
3BHK129.78101
0%

Construction Progress

Building No 1 Type C and C1

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks20%
Stilt Floor100%

Building No 10 Type D

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Building No 11 Type D1

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Building No 12 Type A1

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Building No 13 Type A and A1

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Building No 14 Type A and A1

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Building No 15 Type A and A1

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Building No 16 Type A and A1

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Building No 3 Type B

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Building No 5 Type A and A1

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
Stilt Floor100%

Building No 6 Type A and A1

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.35%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
Stilt Floor100%

Building No 7 Type A and A1

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises70%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises35%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
Stilt Floor100%

Building No 8 Type A and A1

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

Building No 9 Type A

Basement (if any)0%
Excavation0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical meter room, sub-station, receiving station
Energy managemcnt
Fire protection and fire safety requirements
Internal Roads & Footpaths
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Supply
Water conservation /Rain water harvesting