EMERALD WOODS 2

by SHREHIT DEVELOPERS Partnership
Certificate Signed P99000051317
💬 WhatsApp 📞 Call

Project Information

RERA Certificate No.
P99000051317
Registration No.
REA99000136184
Registration Date
2023-06-08
Developer
SHREHIT DEVELOPERS Partnership
Architect
Skyline Architect
Project Bank
KOTAK MAHINDRA BANK LIMITED
Proposed Possession
2029-12-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
3
Project Area
7200.00 sq.m
Total FSI
9277.35
Approved FSI
9262.35
MahaRERA QR
EMERALD WOODS 2
MahaRERA — P99000051317
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors8
Sanctioned8
🅿️Closed Parking40
📅Completion2027-12-31
🏗️Proposed Floors8
Sanctioned8
🚗Open Parking11
🅿️Closed Parking25
📅Completion2025-12-31
🏗️Proposed Floors8
Sanctioned8
🚗Open Parking20
🅿️Closed Parking45
📅Completion2029-12-31

Apartment Configurations

None

Type Carpet (sq.ft) Total Booked Available Status
2Bhk 49.459999084472656 0 0 0
0%
2Bhk 50.16999816894531 0 0 0
0%
2Bhk 50.18000030517578 0 0 0
0%
2Bhk 56.22999954223633 0 0 0
0%
2Bhk 63.25 0 0 0
0%
3Bhk 72.11000061035156 0 0 0
0%

Building No 2

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 56.23 21 4 17
19%
3 BHK 72.11 7 2 5
29%

Building No 3

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 50.18 24 8 16
33%
2 BHK 63.25 2 2 0
100%

Building No 4 A Wing And B Wing

Type Carpet (sq.ft) Total Booked Available Status
2 BHK 49.46 26 0 26
0%
2 BHK 50.17 25 1 24
4%

Construction Progress

BUILDING NO 2

Basement (if any)100%

Building No 2

Excavation100%

BUILDING NO 2

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Building No 2

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUILDING NO 2

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%

Building No 2

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises20%
Overall Percentage of Completion of the work done For the entire Building /Wing39%

BUILDING NO 2

Plinth100%
Podiums (if any) 0%

Building No 2

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING NO 2

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure60%

Building No 2

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.30%

BUILDING NO 2

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%

Building No 2

Stilt Floor80%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure60%

BUILDING NO 3

Basement (if any)100%

Building No 3

Excavation100%

BUILDING NO 3

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%

Building No 3

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50%

BUILDING NO 3

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%

Building No 3

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing71%

BUILDING NO 3

Plinth100%
Podiums (if any) 0%

Building No 3

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING NO 3

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure100%

Building No 3

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%

BUILDING NO 3

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%

Building No 3

Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing60%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

BUILDING NO 4 A WING AND B WING

Basement (if any)30%

Building No 4 A Wing And B Wing

Excavation100%

BUILDING NO 4 A WING AND B WING

External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%

Building No 4 A Wing And B Wing

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%

BUILDING NO 4 A WING AND B WING

Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%

Building No 4 A Wing And B Wing

Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing13%

BUILDING NO 4 A WING AND B WING

Plinth30%
Podiums (if any) 0%

Building No 4 A Wing And B Wing

Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%

BUILDING NO 4 A WING AND B WING

Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%

Building No 4 A Wing And B Wing

Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%

BUILDING NO 4 A WING AND B WING

Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%

Building No 4 A Wing And B Wing

Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth30%
X number of Podiums0%
X number of Slabs of Super Structure0%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station 75%
Energy management
Fire Protection And Fire Safety Requirements
GYMNASIUM
INDOOR GAMING ROOM
Landscaping & Tree Planting 75%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting 100%
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
Call WhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.