List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Esquire

by Jp Infra&Salasar Buildcon Llp Partnership
Certificate SignedP51700030151
EsquireProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700030151
Registration No.
REA51700089176
Registration Date
2025-10-28
Developer
Jp Infra&Salasar Buildcon Llp Partnership
Architect
Tej'S Consultants
Project Bank
HDFC BANK
Proposed Possession
2028-04-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
314
Units Sold
301 (96%)
Buildings
2
Project Area
4752.33 sq.m
Total FSI
22000.00
Approved FSI
18041.99
MahaRERA QR
Esquire
MahaRERA — P51700030151
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors29
✅Sanctioned29
🏠Habitable22
🔢Total Units161
🏡Residential161
🏗️Proposed Floors29
✅Sanctioned29
🏠Habitable21
🔢Total Units153
🏡Residential153

Apartment Configurations

TOWER A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK39.95857114
84%
1BHK41.8116151
94%
1BHK46.57532
60%
2BHK59.4639363
92%
2BHK60.216151
94%

TOWER B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK39.95695514
80%
1BHK41.8121174
81%
1BHK46.67550
100%
2BHK59.4637334
89%
2BHK60.221156
71%

Construction Progress

TOWER A

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises75%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

TOWER B

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
✅Fire protection and fire safety requirements
✅Internal Roads & Footpaths
✅Landscaping & Tree Planting
⬜Open Parking
⬜Sewerage (Chamber, Lines, Septic Tank , STP)
⬜Solid Waste Management And Disposal
⬜Storm Water Drains
✅Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply