List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

EXCELLENCE RESIDENCY 3

by SAI EXCELLENCE DEVELOPERS
Certificate SignedP99000051929
EXCELLENCE RESIDENCY 3Project photos will appear here when available.

Project Information

RERA Certificate No.
P99000051929
Developer
SAI EXCELLENCE DEVELOPERS
Architect
ROSHAN PATIL & ASSOCIATES
Project Bank
HDFC BANK
Proposed Possession
2027-04-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
60
Units Sold
35 (58%)
Buildings
2
Project Area
2217.35 sq.m
Total FSI
2217.35
MahaRERA QR
EXCELLENCE RESIDENCY 3
MahaRERA — P99000051929
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors4
Sanctioned4
🏠Habitable4
🔢Total Units30
🏡Residential30
🏗️Proposed Floors5
Sanctioned5
🏠Habitable5
🔢Total Units30
🏡Residential30

Apartment Configurations

BUILDING NO 17 WING A

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK25.32404
0%
1BHK28.52101
0%
1BHK30.8216016
0%
1BHK30.99404
0%
2BHK39.57101
0%
2BHK42.32404
0%

BUILDING NO 17 WING B

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK25.32303
0%
1BHK28.52101
0%
1BHK30.8216016
0%
1BHK30.99404
0%
1RK16.56101
0%
2BHK39.57101
0%
2BHK42.32404
0%

Construction Progress

BUILDING NO 17 WING A

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

BUILDING NO 17 WING B

Basement (if any)0%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings100%
Electrical meter room, sub-station, receiving station100%
Energy managemcnt
Fire protection and fire safety requirements
Internal Roads & Footpaths100%
Landscaping & Tree Planting100%
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)100%
Solid Waste Management And Disposal
Storm Water Drains100%
Street Lighting100%
Treatment And Disposal Of Sewage And Sullage Water100%
Water Supply100%
Water conservation /Rain water harvesting100%