Flowervalley

by Siddhivinayak Enterprises
Certificate SignedP51700016519
FlowervalleyProject photos will appear here when available.

Project Information

RERA Certificate No.
P51700016519
Developer
Siddhivinayak Enterprises
Project Bank
INDUSIND BANK
Proposed Possession
2024-12-31
Revised Possession
1900-01-01
Extended Possession
2024-12-31
Units Sold
0
Buildings
2
Project Area
15400.00 sq.m
Total FSI
3314.56
Approved FSI
404.00
MahaRERA QR
Flowervalley
MahaRERA — P51700016519
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors6
Sanctioned6
🏗️Proposed Floors6
Sanctioned6

Apartment Configurations

LILLY

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHK31.25404
0%
1BHK36.5320020
0%
1BHK39.53404
0%
1BHK40.63808
0%

LOTUS

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK31.25413
25%
1BHK36.5320218
10%
1BHK39.53431
75%
1BHK40.63826
25%

Construction Progress

LILLY

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

LOTUS

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
Stilt Floor100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical meter room, sub-station, receiving station
Energy managemcnt
Fire protection and fire safety requirements
Internal Roads & Footpaths
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Supply
Water conservation /Rain water harvesting