Project Information

RERA Certificate No.
P99000017287
Developer
Galaxy Shine Developers
Project Bank
Tamilnad Mercantile bank Ltd
Proposed Possession
2022-12-30
Revised Possession
1900-01-01
Extended Possession
2025-12-31
Buildings
3
Project Area
3097.00 sq.m
Total FSI
2787.32
MahaRERA QR
Galaxy Emperia Phase-1
MahaRERA — P99000017287
Scan to verify on MahaRERA portal

Wing-wise Details

🅿️Closed Parking1
📅Completion2021-12-31
📅Completion2021-12-31
📅Completion2021-12-31

Apartment Configurations

Building No-2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
FLAT41.47202
0%
FLAT42.35844
50%
FLAT47.85826
25%
SHOP10.0303
0%
SHOP14.5211
50%
SHOP26.86202
0%

Building No-3

TypeCarpet (sq.ft)TotalBookedAvailableStatus
FLAT30.37431
75%
FLAT30.851293
75%
FLAT33.6431
75%

Building No-6

TypeCarpet (sq.ft)TotalBookedAvailableStatus
FLAT25.43422
50%
FLAT26.68110
100%
FLAT26.75220
100%
FLAT27.45431
75%
FLAT27.55431
75%
FLAT27.92431
75%
FLAT28.5431
75%
FLAT28.91110
100%
FLAT28.95110
100%
FLAT29.73110
100%
FLAT31.25431
75%

Construction Progress

Building No-2

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises40%
Overall Percentage of Completion of the work done For the entire Building /Wing52%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.80%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Building No-3

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing85%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Building No-6

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing90%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply100%
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.
This website is for the use of Actual Home Buyers/Renters and Owners and Property Investors only.
👋 Looking for the right project? Let me help you find it!
🏗️
MPE Project Advisor
● Online now