📞 +91 98200 30685✉️
RERA: A51800043517

Gargi Hills

by Gargi Builder and Developers
Kept in AbeyanceP99000018173

Project Information

RERA Certificate No.
P99000018173
Developer
Gargi Builder and Developers
Project Bank
Bassein Catholic Co-operative Bank Ltd
Proposed Possession
2026-12-30
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Buildings
3
Project Area
4000.00 sq.m
Total FSI
6214.00
MahaRERA QR
Gargi Hills
MahaRERA — P99000018173
Scan to verify on MahaRERA portal

Wing-wise Details

🚗Open Parking116
🅿️Closed Parking26
📅Completion2025-12-31
🅿️Closed Parking12
📅Completion2025-12-31
🅿️Closed Parking2
📅Completion2025-12-31

Apartment Configurations

Gargi Classic

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1 BHK28.59472522
53%
1 BHK29.9413121
92%
1 BHK30.66402713
68%
1 BHK30.82707
0%
1RK20.81707
0%
2 BHK40.612111
92%
DUPLEX70.73642
67%

Gargi Classic Square

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Commercial88.2101
0%
Commercial89.14404
0%

Residential Bungalow

TypeCarpet (sq.ft)TotalBookedAvailableStatus
Residential Bungalow156.4110
100%

Construction Progress

Gargi Classic

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate35%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises85%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises50%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.93%
Stilt Floor95%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing65%
X number of Basement(s) and Plinth100%
X number of Podiums0%
X number of Slabs of Super Structure100%

Gargi Classic Square

Excavation0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0%
Stilt Floor0%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0%
X number of Basement(s) and Plinth0%
X number of Podiums0%
X number of Slabs of Super Structure0%

Residential Bungalow

Excavation100%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100%
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100%
Overall Percentage of Completion of the work done For the entire Building /Wing100%
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100%
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100%
Stilt Floor100%
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100%
X number of Basement(s) and Plinth100%
X number of Podiums100%
X number of Slabs of Super Structure100%

RERA Registered Amenities

Aggregate area of recreational Open Space
Community Buildings
Electrical Meter Room, Sub-Station, Receiving Station
Energy management
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Open Parking
Sewerage (Chamber, Lines, Septic Tank , STP)
Solid Waste Management And Disposal
Storm Water Drains
Street Lighting
Treatment And Disposal Of Sewage And Sullage Water
Water Conservation, Rain water Harvesting
Water Supply
CallWhatsApp
✉️

Get in Touch

Our team will connect with you shortly

+91
🔒 Your details are secure with us
⚡ If need urgent details +91 98200 67525 for further details.