List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

Gopeshwar Apartment

by Mca Constructions
Certificate SignedP51800005914
Gopeshwar ApartmentProject photos will appear here when available.

Project Information

RERA Certificate No.
P51800005914
Registration No.
REA51800010668
Developer
Mca Constructions
Project Bank
ICICI BANK
Proposed Possession
2025-12-30
Revised Possession
2025-12-30
Extended Possession
1900-01-01
Units Sold
0
Buildings
4
Project Area
4750.10 sq.m
Total FSI
4750.10
MahaRERA QR
Gopeshwar Apartment
MahaRERA — P51800005914
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors9
✅Sanctioned9
🏗️Proposed Floors9
✅Sanctioned9
🏗️Proposed Floors9
✅Sanctioned9
🏗️Proposed Floors9
✅Sanctioned9

Apartment Configurations

A WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHKTYPE145.1521156
71%
2BHKTYPE155.65770
100%

B WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHKTYPE141.71752
71%
1BHKTYPE245.15761
86%
2BHKTYPE155.65770
100%

C WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHKTYPE144.9614113
7%
2BHKTYPE165.2214212
14%

D WING

TypeCarpet (sq.ft)TotalBookedAvailableStatus
1BHKTYPE144.9614014
0%
1BHKTYPE247.57707
0%
2BHKTYPE163.55707
0%

Construction Progress

A WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

B WING

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises100%
Slabs of Super Structure10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
Stilt Floor100%

C WING

Basement (if any)0%
Excavation10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

D WING

Basement (if any)0%
Excavation5%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Plinth0%
Podiums (if any)0%
Sanitary Fittings within the flats / premises0%
Slabs of Super Structure0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
Stilt Floor0%

RERA Registered Amenities

⬜Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station50%
⬜Energy managemcnt
⬜Fire protection and fire safety requirements
⬜Internal Roads & Footpaths
⬜Landscaping & Tree Planting
⬜Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
⬜Solid Waste Management And Disposal
✅Storm Water Drains50%
⬜Street Lighting
⬜Treatment And Disposal Of Sewage And Sullage Water
✅Water Supply
✅Water conservation /Rain water harvesting

Latest Mumbai Property News