Govardhan KunjProject photos will appear here when available.
Project Information
RERA Certificate No.
P99000051299
Registration No.
REA99000139298
Registration Date
2023-06-08
Developer
Bhakti Nilayam Private Limited Company
Architect
Sulakshana Telang and Associates
Project Bank
SBM BANK INDIA LIMITED
Proposed Possession
2027-09-01
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Total Units
80
Units Sold
80 (100%)
Buildings
5
Project Area
16000.00 sq.m
Total FSI
8423.04
Approved FSI
8423.04
Govardhan Kunj
MahaRERA — P99000051299
MahaRERA — P99000051299
Scan to verify on MahaRERA portal
Wing-wise Details
🏗️Proposed Floors4
✅Sanctioned4
🏠Habitable4
🔢Total
Units4
🏡Residential4
🏗️Proposed Floors4
✅Sanctioned4
🏠Habitable4
🔢Total
Units64
🏡Residential64
🏗️Proposed Floors4
✅Sanctioned4
🏠Habitable4
🔢Total
Units4
🏡Residential4
🏗️Proposed Floors4
✅Sanctioned4
🏠Habitable4
🔢Total
Units4
🏡Residential4
🏗️Proposed Floors4
✅Sanctioned4
🏠Habitable4
🔢Total
Units4
🏡Residential4
Apartment Configurations
Building No 10 Type E
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 1BHK | 46.78 | 8 | 8 | 0 | 100% |
| 3BHK | 101.12 | 12 | 12 | 0 | 100% |
Building No 7 Type D
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 2.5BHK | 72.98 | 5 | 5 | 0 | 100% |
| 2BHK | 61.64 | 15 | 15 | 0 | 100% |
Building No 8 Type D
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 2.5BHK | 72.98 | 5 | 4 | 1 | 80% |
| 2BHK | 61.64 | 15 | 14 | 1 | 93% |
Building No 9 Type D
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 2.5 BHK | 72.98 | 5 | 0 | 5 | 0% |
| 2BHK | 61.64 | 15 | 0 | 15 | 0% |
Building no 11 Type F
| Type | Carpet (sq.ft) | Total | Booked | Available | Status |
|---|---|---|---|---|---|
| 3BHK | 101.12 | 20 | 19 | 1 | 95% |
Construction Progress
Building No 10 Type E
Building No 7 Type D
Building No 8 Type D
Building No 9 Type D
Building no 11 Type F
RERA Registered Amenities
✅Aggregate area of recreational Open Space
✅Community Buildings80%
✅Electrical meter room, sub-station, receiving station
⬜Energy managemcnt
✅Fire protection and fire safety requirements100%
✅Internal Roads & Footpaths85%
✅Landscaping & Tree Planting50%
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)100%
⬜Solid Waste Management And Disposal
⬜Storm Water Drains
✅Street Lighting50%
✅Treatment And Disposal Of Sewage And Sullage Water100%
✅Water Supply100%
⬜Water conservation /Rain water harvesting