List propertyWhatsApp
Best dealsNew projectsProjects mapBuy a flatRent a flatCommercialBuilders & developersWhy usRERA searchLocalitiesTools & calculatorsNRI hubNews+ List your propertyWhatsApp us
Mumbai property advisory & dataOperating since 1995✓ MahaRERA A51800043517Source-labelled project dataWe reply in minutes on WhatsApp

GREEN PARK 2

by KAWALI BUILDERS Partnership
Certificate SignedP99000029642
GREEN PARK 2Project photos will appear here when available.

Project Information

RERA Certificate No.
P99000029642
Registration No.
REA99000089353
Registration Date
2021-06-14
Developer
KAWALI BUILDERS Partnership
Architect
En Con
Project Bank
BASSEIN CATHOLIC COOPERATIVE BANK LIMITED
Proposed Possession
2026-07-31
Revised Possession
1900-01-01
Extended Possession
1900-01-01
Units Sold
0
Buildings
1
Project Area
446.35 sq.m
Total FSI
561.04
Approved FSI
561.04
MahaRERA QR
GREEN PARK 2
MahaRERA — P99000029642
Scan to verify on MahaRERA portal

Wing-wise Details

🏗️Proposed Floors7
✅Sanctioned7

Apartment Configurations

GREEN PARK 2

TypeCarpet (sq.ft)TotalBookedAvailableStatus
2BHK35.62633
50%
3BHK51.42642
67%
3BHK53.8651
83%
Shop22.63101
0%
Shop27.55101
0%

Construction Progress

GREEN PARK 2

Basement (if any)100%
Excavation100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises92%
Plinth100%
Podiums (if any)0%
Sanitary Fittings within the flats / premises80%
Slabs of Super Structure100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
Stilt Floor100%

RERA Registered Amenities

✅Aggregate area of recreational Open Space
⬜Community Buildings
✅Electrical meter room, sub-station, receiving station10%
✅Energy managemcnt10%
⬜Fire protection and fire safety requirements
✅Internal Roads & Footpaths10%
✅Landscaping & Tree Planting10%
✅Open Parking
✅Sewerage (Chamber, Lines, Septic Tank , STP)10%
✅Solid Waste Management And Disposal10%
✅Storm Water Drains10%
✅Street Lighting10%
✅Treatment And Disposal Of Sewage And Sullage Water10%
✅Water Supply10%
✅Water conservation /Rain water harvesting10%

Latest Mumbai Property News